Modern Railways – April 2019

(Joyce) #1

20 Modern Railways April 2019 http://www.modern-railways.com


Infrastructure News


FUNDING FOR FENLAND PLATFORM EXTENSIONS
THE DEPARTMENT for Transport
has approved a funding package
of around £27 million to allow
Network Rail to extend station
platforms at Waterbeach and
Littleport, on the line between
Cambridge and King’s Lynn. The

work will allow eight-car trains to
be introduced on peak services,
increasing capacity on the line. Both
platforms at Waterbeach will be
extended to 167 metres in length,
while at Littleport platform 2 will
be similarly extended and step-free

access provided to platform 1. New
stabling will also be created at King’s
Lynn to support the longer trains.
Work is expected to start in October
and be completed in summer 2020,
with eight-car services operated by
Govia Thameslink Railway expected

to begin in December 2020.
Network Rail says the project is one
of the first to progress through the
new Rail Network Enhancements
Pipeline process, which DfT and
NR now use to manage delivery
of new rail infrastructure.

BARKING APPLICATION SUBMITTED
C2C HAS submitted a planning
application to the London Borough
of Barking & Dagenham for
improvements at Barking station.
Applications for planning
approval and listing building
consent have been submitted,
which seek to provide increased
capacity at the station. If approval
is received, construction could
begin as early as October.
The aim of the work is to improve
access and reinstate much of the
original architectural language
at the station, which is the only
Grade II-listed 1950s railway
station in London. A proposed first
phase, with designs developed by
architect Weston Williamson and
Partners, involves refurbishment
of the station ticket hall, including
a redesign of the concourse and
construction of a second gateline
to double the number of ticket
gates, as well as increasing the size

of the station’s entrances, creating
new retail space and new toilets.
The ticket hall proposal has
been established as Phase One in
the ambitions of the Barking Town
Centre Regeneration Scheme.
Phase Two would introduce an
interchange bridge at the station

to provide step-free access and
interchange between the platforms
and ticket hall, for which c2c
has submitted an application to
the Department for Transport’s
Access for All fund. The third
phase incorporates an oversite
development above the station.

Improved access proposed: rendition of Barking station after work.

Sub-surface


signalling set


to go live
TRANSPORT FOR London was
aiming to go live with the first
section of automatic signalling
on the London Underground’s
sub-surface lines over the
weekend of 16-17 March, after
this issue went to press.
Thales is supplying
Communications Based Train
Control (CBTC) equipment under
the Four Lines Modernisation
(4LM), with the aim of delivering a
series of timetable enhancements
by 2023. Introduction is planned
across 15 Signalling Migration
Areas (SMAs), beginning with
the Hammersmith branch.
TfL’s Major Projects Director Stuart
Harvey told TfL’s Programmes and
Investment Committee on 6 March
that a new version of software
had been introduced the previous
weekend along with successful
trial runs using the CBTC system.
He confirmed the aim was to go
live with the system between
Hammersmith and Latimer Road
on 16-17 March. He also told the
committee the CBTC equipment
had been installed across the next
five migration areas, covering
the entirety of the Circle Line, in
preparation for these to follow.
The go-live of the first migration
area had initially been targeted
for June 2018 but was postponed
while software issues were
resolved. Mr Harvey told the
Programmes and Investment
Committee the aim was to
commission CBTC signalling across
the Circle Line by the end of this
year, potentially supporting an early
timetable uplift in March 2020.

SIEMENS FOR SOUTH LONDON SIGNALLING
NETWORK RAIL has awarded
Siemens a contract for signalling
renewals in the Catford loop and
Brixton area of south London.
Valued at around £2 million, the
deal will see Siemens lead through

the first three stages of the GRIP
process (output definition, feasibility
and option selection). A contract
notice explains the objectives of
the project are to renew life-expired
assets and improve reliability and

performance. The work incorporates
targeted renewal of the Herne
Hill interlocking with re-control
to Three Bridges Rail Operating
Centre (ROC), full resignalling of
the Stewart’s Lane interlocking

with a similar recontrol, along
with the parallel renewal of
Voltaire Road switches and
crossings, provision of Automatic
Route Setting (ARS) and passive
provision for Traffic Management.

020-021_MR_Apr 2019_infrastructure.indd 20 12/03/2019 15:

Free download pdf