Modern Railways – April 2019

(Joyce) #1

http://www.modern-railways.com April 2019 Modern Railways 65


away for reuse in sidings in the Portsmouth area.
Colas’s Kirow 1200 crane was used for the heavy
lifting, with another Kirow being put on standby
at Tonbridge for the duration of the project in
light of the time-sensitive critical nature of this
section of the job. Speed limits here are 70mph
on the slows and 90mph on the fasts and the aim
was to hand back the fasts at the full linespeed.
While the Colas team was beavering away on
the track replacement, staff from Dyer & Butler
were working on Balcombe Tunnel. This is one of
the longest tunnels on the route and the Victorian
brick culvert drainage system had suffered from a
build-up of silt and other debris, along with some
brickwork degradation. As a result, flooding after
rainfall was damaging the signalling and power
supply system and some action was necessary.
Meanwhile, advantage was taken of the blockade
at Balcombe station to renew the footbridge dating
from the 1970s, which was in poor condition.
As at other stations in the blockade area, general
repairs and repainting were undertaken and the
driver-only operation mirrors removed. Modern
stock on the Victoria and Thameslink routes
has on-board cameras to allow the driver to
monitor door operation on screens in the cab;
the mirrors on the platforms are redundant.

OTHER STRUCTURES


Haywards Heath Tunnel is another one that was
suffering from poor drainage, with work needed
to improve drains in the tunnel. Once the water
was out of the tunnel the problem was not over
as this area of Wealden clay has notoriously poor
drainage and water from the tunnel, coupled

with runoff from neighbouring agricultural fields,
was flooding the trackbed. The solution was
to sink a drainage shaft south of the tunnel.
In Clayton Tunnel, ground water pressure was
causing water to seep through the brickwork
and damaging mortar joints, increasing the
chance of material falling out of the tunnel
lining and potentially damaging trains and
delaying services. In the blockade patch repairs
of brickwork were undertaken and 650 yards of
track were renewed. 1,400 yards of cable were
secured and 1,000 yards of scrap rail cleared.
One of the most iconic structures on the
Brighton main line is the majestic 1848-built
Ouse Valley viaduct. Here, the parapet has been
repaired, conductor rail renewed, the ballast
cleaned and the drainage refurbished.

SIGNALLING


The largest chunk of money spent in the blockade
went on upgrading signalling between Haywards
Heath and Preston Park. The signalling control and
power system was last renewed in 1982 and had
an increasingly-onerous maintenance requirement.
Fibre optics have been installed to replace copper
signalling wires and light-emitting diode signals
have superseded old-fashioned filament signal
heads. Track circuits have been renewed.

This stretch of track is controlled from the
Area Signalling Centre at Three Bridges. The ASC
does not currently have the benefit of Automatic
Route Setting, but Network Rail plans to have
this installed by March 2020. At some point in
the future the ASC’s area will migrate into Three
Bridges Rail Operating Centre, which already
controls the Thameslink route from Anerley to
Kentish Town through the central London core.

OTHER WORK


Thousands of metres of conductor rail dating
from the Southern Railway’s original electrification
in the 1930s were replaced at Folly Hill during
the blockade. Conductor rail was also renewed
at Burgess Hill station, while at Preston Park, the
defective bearers on a set of points were renewed.
Work was also undertaken on the branch to
Lewes through Plumpton, with signal heads
converted and general maintenance undertaken.
Thanking passengers for putting up with the
disruption of the blockade, John Halsall, Network
Rail South East’s managing director, said: ‘We’ve
been able to complete major work to the ageing
infrastructure which has caused so many delays
in the past, as well as repairs in the Victorian-era
tunnels which were prone to flooding. All of this
means we can provide a more reliable service.’ a

BIGGEST BUS REPLACEMENT OPERATION EVER


The railway authorities took no chances when
providing alternative options for travel on the
Brighton main line during the February blockade.
The car park at Three Bridges was commandeered
as a bus station, with marquees as shelter and an
extensive queuing system put in place. From here,
what is billed as the country’s biggest-ever bus
replacement operation (with 536 drivers and over
240 vehicles on weekdays) was scheduled to serve
intermediate stations to the south. As it was
half-term week, many buses normally employed
on school runs were available for this operation.
Brighton and Hove passengers, meanwhile,
could reach London by train on services diverted
via the Arun Valley line. This option came with
quite a time penalty – 2hr 15min journey time as
opposed to an hour normally – but did avoid the
inconvenience of using buses. Coffee vouchers
were handed out to users of this service to sugar
the pill.
Network Rail fettled up the Arun Valley line
before the blockade in an effort to keep everything
running as smoothly as possible, with a drive to
eliminate wet beds on the route and an additional

chainsaw gang stationed at Arundel 24/7 ready to
deal with any vegetation issues.
As an additional measure for season ticket
holders, 2,800 car park spaces were booked in
the long-term car park at Gatwick (which had the
capacity as February is a quiet time for flying), with
a fleet of 12 bendy buses shuttling rail passengers
to an entrance to platform 7 on Gatwick station. As
the Gatwick Express started from the airport during
the blockade, finding a seat was easier than in
normal operation (when some services arrive from
the coast already well-loaded).
But the biggest triumph of all was the
pre-blockade publicity campaign, fronted by an
eye-catching Sammy the Seagull figure in hi-vis kit.
‘Pre-blockade awareness was very high: surveys
in January showed 84% of the passengers asked
were aware of our activity’ reports Andrew Wood
of Network Rail’s 3B2B project team. This resulted in
a big fall in travel, down 67% for the week against
the expected 25%. Thus much of the alternative
provision did not turn out to be needed, with the
queuing systems thankfully standing idle most of
the time.

Vaulting the valley: a Class 700 crosses the impressive
Ouse Valley viaduct on 23 August 2016. The conductor
rail on the viaduct has been replaced. John Vaughan

062-065_MR_Apr 2019_brighton upgrade.indd 65 11/03/2019 17:25

Free download pdf