Modern Railways – April 2019

(Joyce) #1

8 Modern Railways April 2019 http://www.modern-railways.com


News Front


GWR ANGLING FOR SPARKS


TIMETABLE IN DECEMBER


Service intensification does not depend on completion of wires to Cardiff


GREAT WESTERN Railway is
hoping to bring passengers the
benefits of electrification between
Cardiff and London at the December
timetable change.
When Network Rail confirmed
that the energisation date for the
final section of electrification,
between Bristol Parkway and Cardiff
Central, had been deferred to
November 2019, it appeared that
service changes to capitalise on the
project’s completion would also
have to be deferred. Following the
difficulties encountered last year,
the rail industry as a whole is taking
a more cautious approach to major
timetable changes, particularly those
which are dependent on timely
completion of infrastructure works.
However, the performance of
the Intercity Express Trains between
Bristol Parkway and Paddington,
where electrification is complete,
has inspired confidence at GWR
that the proposed additional
services could be operated from
December without significant
risk to performance, regardless of
whether electrification in South
Wales is completed in November.

SPEED-UP


Headline improvements are a
15-minute reduction in journey
times between South Wales and
Paddington, and the doubling of
services between Bristol Temple
Meads and Paddington, exploiting

the recently completed four-tracking
of Filton Bank, north of Temple Meads.
‘Some of the Bristol fast services might
be introduced slightly later’ said GWR
managing director Mark Hopwood.
GWR proposes to increase service
frequency from two to three trains
per hour from Cardiff to London in
the morning peak and from London
to Cardiff in the evening peak. One
of those trains per hour, working
from and to Swansea, would omit
some intermediate station calls to
save slightly more than 15 minutes.
‘The electrification work is moving
forward at a steady pace. We’ve
got confidence that that will come
in,’ said Mr Hopwood. ‘Even if we
didn’t have the electrified railway
west of Bristol Parkway, it wouldn’t
put the whole timetable at risk.’
The outcome of GWR’s bidding
for the proposed timetable
changes will not be known until
late spring or early summer.
Mr Hopwood acknowledged
that GWR’s performance last year
had been affected by line closures
and other difficulties, including
timescales for crew training being
compressed as a consequence of
late completion of earlier sections
of electrification. Performance had
improved significantly, and fewer
trains were being short formed. Last
year’s short formations included
five-car IETs frequently replacing
eight-car HSTs. Five-car IETs are still
occasionally deployed, but only

as a last resort and sometimes to
avoid cancelling a service following
disruption, said Mr Hopwood.
The 10-car IET formations can be
split to provide two trains in such
circumstances, a flexibility which
was not available with HSTs.

TURBOS TO POMPEY


On the inter-urban route between
Cardiff and Portsmouth Harbour,
five-car trains were now being
deployed more consistently,
Mr Hopwood said, some being
Class 166+165 formations and others
Class 158s. Some passengers are
dissatisfied with the 3+2 seating
of the former Thames Valley
commuter stock, but Mr Hopwood
said 2+2 seating was available
in former first class sections.
The route connects several
cities and carries large numbers of
passengers into their nearest city.
Mr Hopwood said short-distance
passengers wanted different
things from their trains than the
longer-distance passengers. The
long-term solution was to create
a limited stop service, but this
could only happen with sufficient
infrastructure and rolling stock to
enable provision of local services
without loss of service frequency
for users of the smaller stations.
Another option for the future is
deployment of bi-mode trains, such
as Class 769 Flex units, between
Cardiff and Bristol Temple Meads,

where the current journey time
is a cause of complaint and there
are plans for several additional
stations. Electric operation
between Cardiff Central and
Patchway would enable faster
acceleration from stations, which
Mr Hopwood said would generate
a small saving in journey times.
The Welsh Government has
commenced a £50 million project
to create a park and ride station
at Llanwern, with stabling sidings
for special event days, and is
co-funding the planned Cardiff
Parkway station, east of Cardiff
Central. Monmouthshire County
Council has been promoting a
‘walkway’ station at Magor, west
of Severn Tunnel Junction.
Mr Hopwood said it was important
to consider the impact of any new
stations on journey times for existing
passengers. While bi-mode operation
was a possibility for the future, GWR
was not currently planning to use
its Class 769s as far west as Bristol.
He confirmed that GWR could
operate 12-car Class 387 formations
from London to Cardiff for weekend
events in the Welsh capital that
draw large numbers of spectators
from England. For major events
in Cardiff on weekday evenings,
Class 387s could be sent onwards
from their Swindon base after
the evening peak to help with
the surge of passengers requiring
homeward transport. Rhodri Clark

GWR trains at Cardiff Central: on 26 February 2019, an
electrification gantry frames a five-car Class 165+
formation, flanked by GWR IETs. Gwion Clark

008-009_MR_Apr 2019_news.indd 8 12/03/2019 14:

Free download pdf