clarification capabilities; and expand-
ing the plant to bring its capacity up
to an average of 2,800 tons per day,
boosting the mill’s production by 27%
while simultaneously cutting costs by
the same margin. “One of the things
our team has been good at is identify-
ing new opportunities,” says Buncic.
“We’ve done that with El Mochito,
we’ve done it with Lagoa Salgada.
In the mining space today, there are
a lot of great opportunities, and we
have an excellent network of partners
who want to work with us across the
financial gamut as we look to grow
the company.”