Flight International – 6 August 2019

(Dana P.) #1

Cover Story


10 | Flight International | 6-12 August 2019 flightglobal.com

L


ong-time Boeing customer
Southwest Airlines is arguably
the carrier most affected by the
continued grounding of the 737
Max, with a fleet of more than 30 of
the aircraft now parked. As such, it
was unsurprising that Southwest’s
executives used much of the com-
pany’s second-quarter earnings call
to outline how the flight suspen-
sion has disrupted its operations,
finances and fleet plan.
Assuming regulators approve
the 737 Max to fly again in No-
vember, Southwest aims to have
at least 30 of the aircraft operating
by 6 January 2020, senior man-
agement said on the 25 July call.
The Dallas-based carrier pulled
all 34 of its 737 Max aircraft from
service when the grounding came
into effect in March, prompting it
to cancel tens of thousands of
flights and rack up $175 million in
related costs in the second quarter.
On 25 July, Southwest said it
had removed 737 Max flights
from another two months of
schedules, pushing to 6 January
the date it expects the aircraft to
return to service.
“Assuming regulatory approval
to return the Max to service by
early November, our baseline plan
would be to control the process so
we could provide the network at
least 30 Max aircraft... by January
6,” Southwest chief operating of-
ficer Mike Van de Ven says. “Then
we would ramp up from there in a
controlled fashion depending on
the delivery schedules.”

timetable doubts
Southwest concedes that the
timeline remains uncertain,
noting that the process for ap-
proving the 737 Max is in the
hands of the US Federal Aviation
Administration (FAA).
Still, based on information from
Boeing, Southwest expects to re-
ceive 16 new 737 Max from the
airframer in 2019, including seven
leased aircraft. But the majority of
deliveries expected this year have
now been pushed into 2020.

Fleet Kristin majcher Buenos Aires

southwest grapples with max absence


Carrier most affected by grounding of re-engined 737 is hopeful that narrowbody can resume service on 6 January

“We don’t have an update to
our contractual delivery schedule
with Boeing at this point, which
shows 41 remaining deliveries
this year,” says Southwest’s chief
financial officer Tammy Romo.
“But we expect the majority of
those will shift to 2020.”
Southwest is holding some
older aircraft longer to cover ca-
pacity requirements until the Max
is approved to re-enter service: the
airline plans to retire 11 737-700s
this year instead of 18, Romo says.
Southwest ended the second
quarter with 753 aircraft and has
not taken delivery of any more
since the Max grounding began,
Romo says.
Southwest’s latest fleet plan
has the carrier resuming Max
flights several months later than
competing airlines estimate.
American Airlines, for instance,
has removed the re- engined nar-
rowbody from its schedules
through 2 November. American
executives said on 25 July that they
are not ready to push the estimated
service-resumption date further
into the future.
However, in a research note is-
sued on the same date, JPMorgan
analysts called American’s No-
vember timeline “unrealistic”.
Boeing is sticking to its plans
to deliver an updated software

package to regulators in Septem-
ber, and it expects the FAA will
clear the aircraft to fly early in the
fourth quarter.
But the agency’s acting
administrator Dan Elwell has
raised doubts that the approval
process will conform to Boeing’s
latest timeline.

“We don’t have a timeline.
Don’t have October. Don’t have
August. Don’t have 2021,” Elwell
said, according to Reuters.
Regulators have repeatedly
insisted they will clear the Max
to fly only after thoroughly
vetting the aircraft.
“We’re unhappy that it’s taken
so long, and we’re in the dark,
just like you are, on a number of
technical matters,” Southwest
chief executive Gary Kelly said in
a CNBC interview to support the
announcement of the quarterly

results. “Our pilots are heavily
engaged and working with Boe-
ing to understand the changes in
terms of the software, and impact
on flight-control systems.”

logistical challenge
Once the grounding is lifted,
Southwest faces the task of bring-
ing into service three groups of
737 Max, Van de Ven says.
One comprises the 34 aircraft it
pulled from service when the
grounding took effect. Southwest
estimates it may need one to two
months to perform maintenance
required to bring those jets, which
are in storage at Victorville, Cali-
fornia, to operational readiness.
Another group includes 737
Max jets already produced and
stored by Boeing, but not yet deliv-
ered. Southwest expects it could
receive those at a rate of three per
week. The third is made up of air-
craft that will be delivered nor-
mally from Boeing as they come
off the production line.
Southwest also reckons it will
need 30 days for pilots to com-
plete new training required by
regulators, assuming that does not
include time in a flight simulator.
Kelly told CNBC he hopes the
airline will be “more or less”
back on track with its fleet plan
by the middle of 2020. ■

Dallas-based airline will require around two months to restore operational readiness of 34 stored jets

etienne Laurent/ePA-eFe

/shutterstock

“We’re unhappy that


it’s taken so long, and


we’re in the dark on a


number of technical


matters”
gary Kelly
Chief executive, southwest Airlines

FIN_060819_010-011.indd 10 31/07/2019 14:

Free download pdf