Project Country City Sector Facility Budget Award Date Award Date CompletionDate^

MOG - Block 58 Onshore Exploration and Production Oman Dhofar Oil Exploration 25,000,000 2019-Q3 EPC ITB 2023-Q3
MOG - Block 59 Offshore Exploration and Production Oman Al Sharqiya Oil Exploration 30,000,000 2017-Q4 On Hold 2021-Q4
Oman Lasso Exploration and Production Karwan - Block 54 Onshore Exploration and Production Oman Al Wusta Oil Exploration 50,000,000 2015-Q3 Engineering & Procurement 2020-Q3


OOCEP - Block 48 Onshore Exploration and Production (Malih Block) Oman Al Dahirah Oil Exploration 30,000,000 2017-Q1 Engineering & Procurement 2021-Q1
OOCEP - Block 60 Concession - Onshore Oman Oman Oil Oil & Gas Field 1,100,000,000 2014-Q1 Construction 2020-Q4
OTTCO - Ras Markaz Crude Oil Park Oman Duqm Oil Oil Storage Terminal 400,000,000 2018-Q3 Engineering & Procurement 2021-Q4
OXY - Expansion of Idd el-Shargi North Dome (ISND Phase-5) Qatar North Dome Oil, Offshore Oil Field 780,000,000 2019-Q4 EPC ITB 2020-Q4
PDO - Amal Steam Phase 1C Surface Facilities Oman Amal Oilfield Oil Enhanced Oil Recovery (EOR) 80,000,000 2016-Q1 Commissioning 2018-Q3
PDO - Amal Steam Phase 1C-2 Oman Amal Oilfield Oil Oil Field Development 500,000,000 2019-Q1 EPC ITB 2024-Q1
PDO - Lekhwair DME Pilot Project Oman Lekhwair Oil Enhanced Oil Recovery (EOR) 25,000,000 2019-Q4 On Hold 2021-Q4
PDO - Marmul Polymer Phase 3 (MPP3) Oman Marmul Oil Oil Field Development 270,000,000 2018-Q1 Engineering & Procurement 2021-Q1
PDO - Yibal Khuff Sudair Field Development Oman Northern Oman Oil Oil Field Development 3,000,000,000 2015-Q2 Construction 2021-Q1
Petrogas Kahil - Block 55 Onshore Exploration and Production Oman Al Wusta Oil Exploration 45,000,000 2013-Q4 Construction 2019-Q1
Port of Fujairah - Dibba Port U.A.E. Sharjah Oil, Infrastructure Oil Storage Terminal 100,000,000 2019-Q4 EPC ITB 2021-Q1
SABIC - ARAMCO - Yanbu - Crude Oil To Chemicals (COTC) Complex Saudi Arabia Yanbu Oil, Industrial Petrochemical Complex 20,000,000,0 00 2020-Q1 FEED 2025-Q4
Saudi Aramco - Annual Onshore Maintain Potential Program (MPP) Saudi Arabia Red Sea Oil Maintenance 5,000,000,000 2014-Q4 Construction 2021-Q2
Saudi Aramco - Duba - Bulk Plant Terminal Saudi Arabia Duba Oil, Industrial Oil Storage Terminal 400,000,000 2019-Q3 EPC ITB 2020-Q1


Saudi Aramco - Jizan Export Refinery - Overview Saudi Arabia Jizan Oil, Petrochemicals, Refining Petroleum Oil Refinery 2,100,000,000 2012-Q4 Construction 2019-Q4
Saudi Aramco - Jizan Export Refinery - Sour Water Stripper & Amine Regeneration Unit Saudi Arabia Jizan Oil, Refining Oil Production 500,000,000 2012-Q4 Construction 2017-Q4
Saudi Aramco - Marjan Cogeneration Independent Steam and Power Project (ISPP) Saudi Arabia Marjan Oil, Power Co-Generation 500,000,000 2019-Q4 EPC ITB 2022-Q4
Saudi Aramco - Marjan Oil Field Expansion - Gas Treatment and Sulphur Recovery Facility Saudi Arabia Marjan Oil, Gas Gas Treatment Plant 375,000, 000 2019-Q2 EPC ITB 2022-Q2
Saudi Aramco - Marjan Oil Field Expansion - Gas Oil Separation Plant (GOSP) Saudi Arabia Marjan Oil GOSP 5,000,000,000 2019-Q1 Engineering & Procurement 2022-Q4
Saudi Aramco - Marjan Oil Field Expansion - Inlet, Storage and Compression Facilities Saudi Arabia Marjan Oil, Gas Gas Compression 375,000,000 2019-Q2 Engineering & Procurement 2022-Q2


Saudi Aramco - Marjan Oil Field Expansion - Offshore Oil Facilities Saudi Arabia Marjan Oil, Offshore Oil Field Development 400,000,00 0 2019-Q3 EPC ITB 2022-Q2
Saudi Aramco - Marjan Oil Field Expansion - Overview Saudi Arabia Marjan Oil, Offshore GOSP 16,000,000,000 2018-Q2 Construction 2022-Q2
Saudi Aramco - Marjan Oil Field Expansion - Utilities, Flare and Pipe Rack Facilities Saudi Arabia Marjan Oil, Industrial Offsites & Utilities 375,000,000 2019-Q2 EPC ITB 2022-Q2
Saudi Aramco - Marjan, Berri, Zuluf and Safaniyah IV Expansion - Overview Saudi Arabia Various Oil, Gas, Offshore Oil & Gas Field 7,000,000,000 2016-Q4 Construction 2022-Q1


Saudi Aramco - Offshore Maintain Potential Programme (MPP) Saudi Arabia Various Oil, Offshore Oil & Gas Field 7,000,000,000 2015-Q1 Construction 2022-Q1
Saudi Aramco - Qatif - GOSP Pipeline Pumping Expansion Saudi Arabia Qatif Oil, Offshore Pipeline 100,000,000 2018-Q1 Construction 2020-Q 1
Saudi Aramco - Safaniya - Debottleneck Onshore Plant Saudi Arabia Safaniyah Oil Oil Production 800,000,000 2019-Q2 EPC ITB 2022-Q1
Saudi Aramco - Safaniyah Expansion Saudi Arabia Safaniyah Oil, Offshore Offshore Platform 1,500,000,000 2017-Q1 Construction 2020-Q2
Saudi Aramco - Southern Area Oil Operations (SAOO) Saudi Arabia Southern Region Oil Oil Field Development 55,000,000 2014-Q3 Engineering & Procurement 2017-Q1
Saudi Aramco - Zuluf Oilfield Expansion Saudi Arabia Zuluf Oil, Offshore Oil Field Development 1,700,000,000 2018-Q1 Engineering & Procurement 2022-Q3
SNOC & ENI - Onshore Acreage Exploration (Areas A, B and C) U.A.E. Sharjah Oil Exploration 1,000,000,000 2019-Q1 Engineering & Procurement 2025-Q4
SRS Middle East FZC - Tank Farm Terminal - Phase 1 U.A.E. Sharjah Oil Bulk Storage 43,560,800 2018-Q3 Construction 2020-Q2