34 PROjECT PRIDE
S. No. Action taken
(Equipment)
Benefits Locations
5 Provision of
covered storage
- For air pollution
control- All stockpiles.
6 Provision of
passenger lift
- To improve safety
working at height level - Better supervision
and control at PH top- Pre-heater
tower and raw
mill
- Pre-heater
7 Provision of
maintenance
platform,
staircase for
poking hole,
inspection door,
and guarding
around the
equipment
- Improves the human
safety - Better supervision
and maintenance at
critical location- At required
locations
- At required
8 Provision of fire
detection system
- Improves general and
electrical safety- Switchgear
rooms, control
rooms, and bag
godown
9 Provision of
gamma ray
indicator
- Switchgear
- To detect the cyclone
jam and reduces
safety hazards at pre-
heater - Pre-heater all
cyclones
10 Wind velocity
and direction
monitoring
- Equipment protection
in event high wind
velocity- Stacker and
reclaimer
- Stacker and
C Reliability initiatives
1 Provision
of magnetic
separators
- Improving the mill
reliability by online
removing of metal
pieces- All mill feeding
conveyors
- All mill feeding
2 Provision of
electrically
operated hoist
- Decreasing the
downtime- All crushers,
roller press,
mill, separators,
PH fan, clinker
breaker
- All crushers,