Dalmia DSP Success Story

(Project Pridr) #1
COmmENCEmENT OF ExECUTION 63

arose during execution and in overcoming all bottlenecks.
A positive and motivational approach with the business
partners worked very well in formalizing all the execution
schedule needs.
In the meantime, the engineering consultant started the
release of civil construction drawings to civil contractors to
provide work fronts immediately on mobilization. On the
auspicious day of 17 September 2018, the ground-breaking
ceremony and Puja were performed for the Dalmia DSP
unit at Rajgangpur marking the start of construction works
at the site.


Ground-breaking ceremony on 17 September 2018