Control Costs


Project cost controlincludes:


o influencing the factors that create changes to the authorized costbaseline;


o Ensuring that all change requests are acted on in a timely manner;


o Managing the actual changes when and as theyoccur;


o Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS
component, by activity, and in total for theproject;


o Monitoring cost performance to isolate and understand variances from the approved cost
baseline;


o Monitoring work performance against funds expended;


o Preventing unapproved changes from being included in the reported cost or resourceusage;


o Informing appropriate stakeholders of all approved changes and associated costs;and


o Bringing expected cost overruns within acceptablelimits.


110.Answer: B.


PMBOK® Guide, pages 261 – 265 , Section 7. 4. 2. 2 ; and Figure 7 – 12


Agood understanding ofthe earnedvalueanalysisisrequired toproperlyinterpretthisgraph.
ReviewtheentireSection 7. 4. 2. 2 forafulldescription.


111.Answer: C.


PMBOK® Guide, page 265 , Section 7. 4. 2. 2 ;


Forecasting


Theprojectmanager'smanualEACisquicklycomparedwitharangeofcalculatedEACsrepresenting
variousriskscenarios.WhencalculatingEACvalues,thecumulativeCPIandSPIvaluesaretypically
used. While EVMdata quickly provide many statistical EACs, only three of the morecommon
methodsaredescribedasfollows:


o EACforecastforETCworkperformedatthebudgetedrate.ThisEACmethodacceptstheactual
projectperformancetodate(whetherfavorableorunfavorable)asrepresentedbytheactualcosts,
andpredictsthatallfutureETCworkwillbeaccomplishedatthebudgetedrate.Whenactual
performance is unfavorable,the assumption that futureperformance will improve should be
acceptedonlywhensupportedbyprojectriskanalysis.Equation:EAC=AC+(BAC–EV)



  1. Answer: A.


PMBOK® Guide, pages 264 – 265 , Section 7. 4. 2. 2


Forecasting


Theprojectmanager'smanualEACisquicklycomparedwitharangeofcalculatedEACsrepresenting
variousriskscenarios.WhencalculatingEACvalues,thecumulativeCPIandSPIvaluesaretypically
used. While EVMdata quickly provide many statistical EACs, only three of the morecommon
methodsaredescribedasfollows: