3.Bidderconferences


4.Dataanalysis


o Proposal evaluation

5.Negotiation


209.Answer:B.


PMBOK® Guide, page 471 , Section12.1.1.6


Organizational Process Assets


Cost-reimbursablecontracts.Thiscategoryofcontractinvolvespayments(costreimbursements)to
thesellerforalllegitimateactualcostsincurredforcompletedwork,plusafeerepresentingseller
profit.Thistypeshouldbeusedifthescopeofworkisexpectedtochangesignificantlyduringthe
executionofthecontract.


Variations can include:


Costplusfixedfee(CPFF).Thesellerisreimbursedforallallowablecostsforperformingthecontract
workandreceivesafixed-feepaymentcalculatedasapercentageoftheinitialestimatedproject
costs.Feeamountsdonotchangeunlesstheprojectscopechanges.


210.Answer:C.


PMBOK® Guide, page 479 , Section12.1.3.6


Make-or-BuyDecisions


Amake-or-buyanalysisresultsinadecisionastowhetherparticularworkcanbestbeaccomplished
bytheprojectteamorneedstobepurchasedfromoutsidesources.


211.Answer:B.


PMBOK® Guide, page 488 , Section12.2.2.5


Interpersonal and Team Skills


Interpersonalandteamskillsthatcanbeusedforthisprocessincludenegotiation.Negotiationisa
discussionaimedatteachingaagreement.Procurementnegotiationclarifiesthestructure,rights,
andobligationsofthepartiesandothertermsofthepurchasessothatmutualagreementcanbe
reachedprior tosigningthecontract.Finaldocumentlanguagereflects allagreementsreached.
Negotiationconcludeswith asignedcontractdocument orother formalagreementthatcanbe
executedbybothbuyerandseller.Thenegotiationshouldbeledbyamemberoftheprocurement
teamthathasthe authorityto signcontracts.Theprojectmanager andother membersofthe
projectmanagementteammaybepresentduringnegotiationtoprovideassistanceasneeded.