Figure 11- 1 shows the percentage of the construction costs for each airport facility from
the total cost.
Figure 11 - 1 Percentage of Construction Cost
The general total estimated cost by the end of Phase III is listed in Table 11-2.
Table 11 - 2Construction Cost of Al-Auja International Airport
No. Item Estimated Cost ($)
1 Runways System 36,923,370
2 Taxiways System 31,770,680
3 Apron Area 116,094833
4 Terminal Building 447,092,100
5 Lighting, Marking, Signage 3,468,515
Total Cost 635,349, 500
15 % 61 %
12 %
11 %
1 %
Percentage of Construction Cost
Terminal Building Apron Area Runways System Taxiways System Lighting,