Palestine International Airport (Al-Auja)

(Noor Al-Dian Rabaya) #1
5

Expansion of Taxiway System through Apron Area
* Earthworks including excavation and backfill of subgrade material.
* Flexible Pavement Works
5.1 Cross Taxiway

5.1.1


Earthworks
1 - Excavation (Cut) m3 421,277 4 1,685,108
2 - Fill (Backfill imported from the site) m3 0 6 -

5.1.2


Flexible Pavement (40cm)
1 - HMA (25cm) m2 47 65 3,023
2 - Base Course(15cm) m3 17,730 40 709,200
5.2 Hangar Taxiway

5.2.1


Earthworks
1 - Excavation (Cut) m3 147,830 4 591.320
2 - Fill (Backfill imported from the site) m3 0 6 -

5.2.2


Flexible Pavement (40cm)
1 - HMA (25cm) m2 30 65 1,950
2 - Base Course(15cm) m3 10,854 40 434,160
5.3 Apron Taxiway

5.3.1


Earthworks
1 - Excavation (Cut) m3 1,137,580 4 4,550,320
2 - Fill (Backfill imported from the site) m3 11183 6 67,098

5.3.2


Flexible Pavement (40cm)
1 - HMA (25cm) m2 189 65 12,285
2 - Base Course(15cm) m3 4,226 40 169,040
Subtotal 8,223,504

6

Expansion of Terminal Building
(Substructure, Superstructure, Internal
finishes, Services)

m2 32,310 4,770 154,118,700

Subtotal 154,118,700