HYDROLOGY 487
Experience of similar structures is very useful at this stage,
especially in evaluating such added constraints as possible
log jams or the infl uence of siltation or erosion (Bureau of
Reclamation^54 ).
Major Spillway Design Floods
Large dams are a particularly challenging design problem
from many viewpoints. In particular, the consequences of
failure due to inadequate spillway design have given rise to
numerous extensive hydrological studies and the develop-
ment of suitable techniques. For such a major structure it is
usual to calculate design fl oods by several methods, as dis-
cussed in such references as Kuiper and Linsley. 52,53
The fi rst method is based on extreme probability theory
as previously discussed in the statistics section. The analy-
sis of extreme independent time series is based on the work
of Fisher and Tipper^11 and is well illustrated by Gumbel.^12
The big question is what level of risk to assume, and prob-
abilities of 1:1000 to 1:10,000 are not uncommon for such
projects. The economic arguments reveal that the spillway
cost is often small compared with the havoc that could
occur if the dam failed. Hence it is quite usual for spillways
to be designed for much more rare events than the design
fl ood used for the rest of the system. Clearly the determina-
tion of the spillway design fl ood involves the incorporation
of a large safety factor, but it is still necessary to make as
good an estimate as possible of the true probability of such
an event.
The second method for estimation of design fl oods is the
maximum probable fl ood^1 approach. The physical processes
involved in producing a fl ood are studied. In some areas,
such as the North-Western part of North America, snowmelt
is the principal factor for large rivers. Elsewhere rain fl oods
may be limiting. Probable maximum precipitation can be
estimated by storm maximization,^55 or by statistical methods.
A simple approach was developed by Hershfi eld^56 and has
been called the poor man’s probable maximum precipita-
tion, the PMPMP. It is necessary to study the weather pat-
terns which produce either high snowmelt or high rainfall
Step Approximation
of unit Hydrograph
Sum of two
unit Hydrograph
Ins. of Rain
C.F.S
500
1000
1500
C.F.S
500
1000
1500
C.F.S
500
1000
1500
(^21)
1
2
2
2
3
3
(^4456)
4
6
6
8
(^24688)
10
(^1010)
Hours
Hours
1Hr.U.H.
2Hr.U.H.
Hours
Hours
1 HOUR UNIT HYDROGRAPH
RAIN-DURATION CURVE
CONSTRUCTION OF 2 HOUR
UNIT HYDROGRAPH 2 HOUR UNIT HYDROGRAPH
PEAK RUN-OFF RAIN
Critical Duration is 4 Hour Storm of 2.5 ins. of Rain,
which produces maximum Run – off of 2810 C.F.S.
U.H.PEAK RUN-OFF-RAIN x U.H.PEAK
1
2
3
4
5
Hour Storm 1.0 inch
1.7
2.0
2.5
2.75
(^1540) 1540 C.F.S
1290
1290
1125
990
2190
2580
2810
2720
Max.
FIGURE 14 Determination of critical storm duration for a given catchment.
C008_003_r03.indd 487C008_003_r03.indd 487 11/18/2005 10:29:33 AM11/18/2005 10:29:33 AM