90 CHAPTER NINE
Check the soil borings for the kind of soil recorded and
the approximate depth the piles must be driven. The accu-
racy of this information is quite important.
Specifications. Check the type of piles required and under
what conditions sheet piling is required. Any requirements
regarding soil conditions, equipment, or other special items
should be noted. Many specifications require that only firms
experienced in driving piles be allowed to do so on the job.
9–20 Pile Checklist
Ty p e :
wood
wood and concrete
H-piles
casing and poured in place
poured in place
precast
wood sheets
steel sheets
precast sheets
bracing
Equipment:
pile driver
compressors
derricks
cranes
9–21 Asphalt Paving
The asphalt paving required on the project is generally sub-
contracted to someone specializing in paving. The general
contractor’s estimator will make an estimate to check the
subcontractor’s price.
Asphalt paving will most commonly be hot-mix and is
generally classified by traffic (heavy, medium, or light) and
use (walks, courts, streets, driveways, etc.).
The estimator will be concerned with subgrade prepara-
tion, subdrains, soil sterilization, insulation course, subbase
course, base courses, prime and tack coats, and the asphalt
paving required. Not all items are required on any given pro-
ject, so the estimator should determine which items will be
required, the material and equipment necessary for each
portion of the work, and the requisite thickness and amount
of compaction.
Specifications. Check the requirements for compaction,
thickness of layers, total thicknesses, and materials required
for each portion of the work. The drawings will also have to
be checked for some of these items. The drawings will show
the location of most of the work to be completed, but the
specifications should also be checked. The specifications and
drawings will list different requirements for the various uses.
(These are called traffic requirements.)
Estimate. The number of square feet (or square yards)
of surface area to be covered is determined, and the thick-
ness (compacted) of each course and the type of materials
required are noted. Base courses and the asphalt paving
are often taken off by the ton, as this is the unit in which
these materials must be bought. The type of asphalt and
aggregate size required must also be noted. Two layers of
asphalt paving are required on some projects: A coarse
base mix may be used with a fine topping mix. Equipment
required may include a steel-wheel roller, trailers to trans-
port equipment, dump trucks, paving machines, and vari-
ous small tools.
To estimate the tons of material required per 1,000 sf of
surface area, refer to Figure 9.44. Different requirements will
be listed for the various uses (walk, driveway, etc.), and the
different spaces must be kept separately.
In many climates, the asphalt paving has a cutoff date in
cold weather, and the paving that is not placed when the
mixing plants shut down will not be laid until the start-up
time in the spring. The plants may be shut down for as long
as four months or more, depending on the locale.
FIGURE 9.44.Approximate Asphalt Paving Materials Tonnage.