Doors and Windows 187
FIGURE 15.2.Window Takeoff.
Aluminum Windows and Curtain Wall. The shapes
for aluminum mullions used in curtain walls or storefronts
are made by an extrusion process and roll forming. Finishes
include mill finish (natural silvery sheen), anodizing (pro-
tective film; it may be clear or a variety of color tones), paint,
lacquer, and colored or opaque coatings. Obviously, the fin-
ish required must be noted, because it will affect the price of
the materials. The specifications will require certain thick-
nesses of metal throughout the construction of the frames.
Care on the job is important, because exposed alu-
minum surfaces may be subject to splashing with plaster,
mortar, or concrete masonry cleaning solutions that often
cause corrosion of the aluminum. Exposed aluminum
should be protected during construction with either a clear
lacquer or a strippable coating. Concealed aluminum that is
in contact with concrete, masonry, or absorbent material
(such as wood or insulation) and may become intermittently
wet must be protected permanently by coating either the
aluminum or the adjacent materials. Coatings commonly
used include bituminous paint and zincchromate primer.
The costs of such protection must be included in and
are part of the cost of the project. If the frames are to be
installed by a subcontractor, the estimator must check to see
whether the subcontractor has included the required protec-
tion in the proposal; if not, the estimator will have to make
an allowance for it. Also, who will apply the protection? If a
strippable coating is used on exposed aluminum, the estima-
tor must note who will remove the coating, whether the sub-
contractor has included this in the price, or whether the
general contractor will handle it. Any piece of work that
must be done costs money, so estimators ensure that all
items are included.
Before the job is bid, the estimator should check the
details showing how the windows are to be installed. They
may have to be installed as the construction progresses
(where the window is built into the wall), or they may be
slipped into openings after the building has been con-
structed. The method is important as there is always a time
lag for approvals, and manufacture (of custom units) and
coordination will be important.
Labor Hours
Windows per Window
Wood
In Wood Frames 2.0 to 3.5
In Masonry 2.5 to 5.0
Metal
In Wood Frames 2.0 to 3.5
In Masonry 2.0 to 4.0
Over 12 s.f. Add 20%
Bow and Bay Windows 2.5 to 4.0
EXAMPLE 15-1 RESIDENTIAL WINDOWS
Determine the quantity of windows for the residence found in
Appendix B. The window schedule (Figure 15.1) typically denotes
all window sizes and types. The estimator simply must verify the list
and count the number of each size and type (Figure 15.2).
FIGURE 15.1.Sample Window Schedule.
Installation:
6 wood windows in masonry
Productivity rate (Figure 15.3) 3 labor hours / window
Labor cost ($)18 hours$12.25 per hour$220.50
18 labor hours
Labor hours6 windows3 labor hours per window
EXAMPLE 15-2 COMMERCIAL BUILDING
Determine the quantity of windows in the small commercial build-
ing found in Appendix A. Figure 15.4 is an excerpt of the window
schedule for that project.
Single hung 3 0 7 0 count 2
Fixed glass 3 0 7 0 count 17
Productivity rate (Figure 15.3) 3 labor hours / window
Labor cost ($)57 hours$12.25 per hour$698.25
57 labor hours
Labor hours19 windows3 labor hours per window
FIGURE 15.3. Labor Hour Productivity
Rates.