Estimating in Building Construction

(Barré) #1

230 CHAPTER TWENTY-ONE


FIGURE 21.3.Warehouse
Square Foot Costs.
From Means Square Foot Cost
Data 2007. Copyright RS Means,
Kingston, MA 781-585-7880; All
rights reserved

From Figure 21.3, the base story height is 24; and from Figure 21.2,
the adjustment for story height is $0.40 per sf per foot of height.


From Figure 21.2, the added cost for a 7 8 dock leveler is $6,225
per leveler.


$2,496,600 — Use $2,500,000 

Total cost$2,471,700$24,900

Dock levelers 4 ea$6,225 per ea$24,900

Base cost ($)30,000 sf$82 .39 per sf$2,471,700

Base cost ($>sf)$82 .39 per sf

Base cost ($>sf)$79 .15 per sf$0 .84 per sf$2 .40 per sf

$2.40 per sf

Add for story height ($>sf)(30¿ 24 ¿)$0 .40 per sf per ft

$2.10 per sf per 100 lf$0.84 per sf

Add for Perimeter ($>sf )(740¿ 700 ¿)> 100 ¿ 21–4 ASSEMBLY ESTIMATING


In assembly estimating, rather than bidding each compo-
nent separately, the components are grouped into assem-
blies, consisting of items that would be installed together
(but not necessarily by the same trade), and then the assem-
bly is bid as a single component. For example, the cost per
linear foot for an 8-foot-high interior wall (consisting of
track, metal studs, insulation, drywall, and paint) may be
determined. Then all 8-foot-high interior walls may be bid
by the linear foot rather than by bidding the track, metal
studs, drywall, insulation, and paint separately.
To create an assembly, the estimator determines the
quantity of materials needed for one unit of the assembly,
linear foot of wall in the case of the interior wall. From these
quantities, the cost for materials, equipment, and labor to
construct one unit of the assembly is then determined. This
Free download pdf