Construction Status :
Delhi - Vadodara SectionPackage Length State Concessionaire Physical Expected
(k.m.) Progress Completion
Date
Pkg 17 32 Madhya JiangXi Construction Engineering 43%
Pradesh (Group) Corporation Ltd. -
MKC Infrastructure Ltd. (JV)
Pkg 18 33 Madhya G R Infraprojects Limited 66%
Pradesh
Pkg 19 30 Madhya JiangXi Construction Engineering 22%
Pradesh (Group) Corporation Ltd. -
MKC Infrastructure Ltd. (JV)
Pkg 20 25 Madhya GHV (India) Pvt Ltd. 52%
Pradesh
Pkg 21 30 Madhya G R Infraprojects Limited 65%
Pradesh
Pkg 22 25 Madhya Larsen & Toubro Ltd. 41%
Pradesh
Pkg 23 25 Madhya G R Infraprojects Limited 44%
Pradesh
Pkg 24 21 Madhya G R Infraprojects Limited 54%
Pradesh
Pkg 25 23 Madhya G R Infraprojects Limited 51%
Pradesh
Pkg 26 30 Gujarat Yet to be Awarded Bids Received -
Under Evaluation
Pkg 27 29 Gujarat GHV (India) Pvt Ltd. 0%
Pkg 28 26 Gujarat GHV (India) Pvt Ltd. 0%
Pkg 29 23 Gujarat PNC Infratech Pvt. Ltd. 15%
Pkg 30 22 Gujarat Patel Infrastructure Limited 0%
Pkg 31 19 Gujarat PNC Infratech Pvt. Ltd. 10%*Status as of 10th September, 2021
Nov'22Jan'23Delhi - Mumbai Expressway