Construction Status
Vadodara – Mumbai Section
*Status as of 10th September, 2021
Package Length State Concessionaire Physical Expected
(k.m.) Progress Completion
Date
Pkg 1 24 Gujarat IRB Infrastructure Developers Ltd. 80%
Pkg 2 32 Gujarat IRCON International Limited 81%
Pkg 3 31 Gujarat Patel Infrastructure Limited 82%
Pkg 4 13 Gujarat Ashoka Buildcon Limited 92%
Pkg 5 25 Gujarat Sadbhav Engineering Pvt. Ltd. 10%
Pkg 6 37 Gujarat G R Infraprojects Limited 0%
Pkg 7 27 Gujarat IRB Infrastructure Developers Ltd. 0%
Pkg 8 36 Gujarat Roadway Solutions India Infra Ltd. 0%
Pkg 9 26 Gujarat Roadway Solutions India Infra Ltd. 0%
Pkg 10 25 Gujarat Roadway Solutions India Infra Ltd. 0%
Pkg 11 26 Maharashtra RKC Infrabuilt Private Ltd. 0%
Pkg 12 26 Maharashtra Montecarlo Limited 0%
Pkg 13 27 Maharashtra G R Infraprojects Limited 0%
Total 355Mar’21Jan' 23JNPT Spur 17 Maharashtra Yet to be awarded Bids Invited
Pkg 1
JNPT Spur 23 Maharashtra Yet to be awarded Bids Invited
Pkg 3
JNPT Spur 27 Maharashtra Yet to be awarded Bids Invited
Pkg 4
JNPT Spur 9 Maharashtra Yet to be awarded Bids Invited
JNPT Spur 15 Maharashtra Yet to be awarded Bids yet to be invited
Pkg 5 (to be developed by MMRDA)
Total 90Oct' 23Delhi Spur
JNPT Spur
Oct' 23Mar' 23Delhi Spur 9 Delhi Dineshchandra R. Agrawal 0%
Pkg 1 Infracon Pvt. Ltd.
Delhi Spur 25 Haryana Dineshchandra R. Agrawal 1%
Pkg 2 Infracon Pvt. Ltd.
Delhi Spur 26 Haryana Dineshchandra R. Agrawal 1%
Pkg 3 Infracon Pvt. Ltd.
Jewar Airport 30 Uttar Yet to be Awarded Bids Yet to be
Connectivity Pradesh Invited
Spur
Total 90