technical NOTES

(Project Pridr) #1

1.4 Executive Summary:
a) Cement and captive power plants are large plant with complex process to
operate and control. As the individual starter are used for control of individual
motor function only like workshops, de-watering pump station, single belt
conveyors, standalone crushers etc. Hence, it is not recommended to use
single starter for process control functions at all.


b) The conventional motor control centre is widely used for large and complex
process control applications. The common uses of the system are in the
cement, power, refineries and petrochemical but now the same is being replaced
by intelligent MCC’s


c) The intelligent motor control centre are the advanced version of conventional
motor control centre and being used for large and complex process like
cement, power, steel, refineries etc. There are hundreds of drives to operate
in sequential mode at a given time. A small delay in fault tracing will lead to
higher rectification costs. Hence, intelligent motor control centre following
benefits to the plant:



  • By reducing fault occurrence frequency of system and Improving system
    reliability

  • By improving fault traceability and decreasing rectification time,

  • By engaging less man power for operation and maintenance,

  • By lowering motor burning rates due to accurate setting and reliable operation,


S. N. Description Standard MCC Intelligent MCC
1 Total cost of the motor control centre in a
cement project in Rs lacs (Integrated Unit)

548 684

2 Total cost of DCS system in complete
cement plant in lacs

832 756

A) SUB TOTAL-A in lacs 1380 1440
1 Cost of cables, cable trays (from MCC
panel to I/O panel) , cable glands and other
Hardware’s in lacs

40 10

B) SUB TOTAL-B 40 10
TOTAL(A+B) 1420 1450
TOTAL IMPACT ON CAPITAL COST DUE TO
INTELLIGENT MCC (Rs. Lacs)

30

1 Total installation and commissioning time for
MCC’s and plant DCS system

75 days 45 days

2 Per day loss due to delay in plant
commissioning @ 50% capacity in Rs lacs

12 12

3 Loss due to delay in plant commissioning as
above in Rs lacs

360 0