Description UOM Requirement
- Selection of Mining Equipment for Lime Stone Mines MECHANICAL
- Limestone Crusher Selection Criteria
- Selection of Limestone Stockpile (Linear v/s Circular)
- Prefebricated Shed v/s Fabricated Shed
- Process Dedusting Filter RABH, PJBH, ESP & Hybrid Filter
- Various Dust Suppression Systems
- Vertical Roller Mill and Roller Press
- Selection of Single String v/s Double String Preheater
- Process Duct Sizing Criteria
- Rotary Screw and Reciprocating Compressors
- Intelligent MCC v/s Conventional MCC ELECTRICAL & INSTRUMENTATION
- Selection of Starter & Speed Control for Preheater, Raw & Cement Mill Fan
- Lab Automation System (Robo Lab)
- Particle Size Analyser (PSD)
- Pre - Fabricated Trays over Fabricated Trays
- Cable Tunnel v/s Overhead Gallery Cable Tunnel v/s Overhead Gallery
- Process Measurement Devices
- Analysis of LT Motor (Cost v/s Efficiency)
- Weighing Concept
- Comparison between Rotoscale / Multicore and Solid Flow Feeder
- Profibus Interface v/s Conventional Interface
- VFD for Bag Filter Fans
- VFD for Air Slide Fans and Root Blower
- Deep Pan Conveyor / Bucket Elevators 14. Selection of Starter & Speed Control for Belt Conveyor /
- Air Insulated Substation v/s Gas Insulated Substation
- Digital Transformation
- LED Fixtures v/s Conventional Lighting Fixtures
- Analysis of Project Data - Cement Plant Civil Work CIVIL
- Selection of Capacity of Raw Meal Silo, Cement Silo & Fly Ash Silo
- Cement Bags Truck Loaders
- Reinforcement Bars Splicing Methods in RCC Construction
- PEB Labour Housing Technical Note
- Comparison of Preheater Stack Options
- RABH Building-Civil Cost Comparison in using Airslide v/s Redller Conveyor IV Technical Notes | A Guide for Cement Technocrats
- Raw Meal Silo Comparison between Bin Inside and Outside
- Comparison of Counterfort & Cantilever Retaining Walls
- Precast Construction in Concrete
- Topographical Survey Through Satellite Imagery
- Inter Grinding v/s Separate Grinding (PSC) PROCESS
- Power Generation by GPP (WHRS)- 4, 5 & 6 Stage Preheater
- Increase in Insulation Thickness in Preheater
- Aluminization with Heat Resistant Painting
- AFR Firing System Comparison
- Impacts of AFR`S Usage
- Kiln Slope 4.5%
- NOx Generation in Cement Plants, its Impact & Control Measures
- Preheater Cyclone Efficiency
- Preheater Cyclone Size
- Coal Mill Booster Fan
- Various Kiln Burners
- Technical Comparison of Latest Generation Clinker Coolers
- Nuisance Bag Filter Design Pressure
- Preheater and Cooler Vent Fan Selection Criteria
- WHRS System WASTE HEAT RECOVERY SYSTEM
- Turbine and Generator
- Air Cooled Steam Condenser
- Electrical and Instrumentation
- No of dumpers to be deployed per excavator Nos. 2.
- Availability %
- No of dumpers required of 55 tons capacity per Excavator Nos.
- Total No. of 55 MT Dumper Requirement Nos.
- Rate of production for 4.2 M3 Excavator in limestone TPD Case 2: 4.2 cu .m Excavator with 35MT Dumpers
- Excavator running hours h/shift
- Excavator capacity for limestone t/shift
- No of shift operation Nos.
- Say TPD
- 35MT dumper TPH @ 4 trips per hour TPH
- No of dumpers to be deployed per excavator Nos.
- Availability %
- No of dumpers required of 35 tons capacity Nos.
- Total No. of 35 MT Dumper Requirement Nos.
- Rate of production for 2.1 M3 Excavator in limestone TPD Case 3: 2.1 cu. m Excavator with 16MT Dumpers
- Excavator running hours h/shift
- Excavator capacity for limestone t/shift
- No of shift operation Nos.
- Say TPD
- No of excavator to be deployed of 2.1 M3 capacity Nos.
- 16MT dumper TPH @ 4 trips per hour TPH
- No of dumpers to be deployed per excavator Nos.
- Availability %
- No of dumpers required Nos.
- Total No. of 16 MT Dumper Requirement Nos.
- No of excavator to be deployed of 4.2 cu. m. size Nos.