technical NOTES

(Project Pridr) #1

From the above options, a cost analysis considered as shown in the following table
and only the large size equipment to be selected.


S. N. Cost Component

Large Size
Machines
(6.5cu.m
Shovel
& 55MT
dumpers

Medium Size
Machines
(4.2cu.m
Shovel & 35MT
dumpers

Small Size
Machines
(2.1cu.m Shovel &
16MT Tippers

1 Excavation & Loading
Cost in Rs./MT (owning &
Operation)

8.31 8.78 8.


2 Transportation Cost
in Rs./MT (owning &
Operation)

11.78 14.90 12.


Total Cost 20.09 23.68 21.
3 Total Man Power 14 25 65


  • Note: Operating cost shall be validated with present condition.
    For a Limestone Mine of 6.6 MTPA in which 5 million tons is the ore and 1.6 million
    ton is the overburden, to minimize the cost of transportation during operation
    stage, the crusher is located at the Mine Pit. This restricts the hauling distance of
    the Limestone or waste to the range of 1 to 1.5km. As a thumb rule higher the
    bench height, lower the cost of raising and keeping in view the crusher feed size of
    1200mm cube, the bench height is decided to be of 10m. As mining is the manpower
    intensive activity and keeping view the administrative problem, always it is
    desirable to reduce the manpower deployment and increase the output per man-shift.
    To re d u ce the traffic on the roads and reduce the exposure of the human for the
    safety risk it is advisable to deploy higher capacity dump trucks.


The Advantages of Using Large Sized Excavator & Dump Trucks in Mines with short
lead, high lift and high volume of handling are as follows:


a. Reduction in manpower and associated cost



  • Workshop crew

  • Mining personnel

  • Supervision team

  • Maintenance Crew


b. Lower Overall Cost per ton



  • Higher Productivity of system

  • Higher Output per Man Shift (OMS)


c. Lower Maintenance and Mining Practice



  • Higher Reliability