switch board, distribution transformers, MCC, PCC etc. By this way more than
50% cable work gets completed along with mechanical erection.
c) From the sub-station to process building, the cable route can be through
underground tunnel depending upon requirement. Clinker Cooler, Coal Mill,
Cement Mill and Packing Plant areas are always preferred with underground
configuration due to cement dust deposition.
d) The Raw Mill, Pyro Section, Water Treatment areas are preferred with over
head configuration due to low dust level. The cable distribution within the
individual building should be always preferred with overhead configuration for
better access, better maintenance, better visibility, etc.