7.4 Cost Comparison of VRM Vs. Roller Press for Raw Grinding Application


Roll Press Vs. VRM Techno-Commercial Comparison Raw Mill System
S.N. Parameters Unit RP VRM
1 Grind ability at VRM Meter kWh/Ton 5.0 5.0
2 Type of Mill Process Roller Press VRM
3 Rated Capacity at 15% residue at 90
micron

TPH 600 640


I) Capital Cost Analysis
1.A Cost of Civil Structures
1 Total Concrete (Raw Mill Building) M3 3638 3902
2 Total Cost of Concrete (@ Rs. 17750/
CUM)

Rs in Lacs 646 693

3 Differential Cost on Concrete Rs in Lacs 0 47
1.B Cost OF FAB.+Erection+Steel
1 Fabrication Items Scope Ton 420 850
2 Cost of steel required for site
fabrication + Erection items @ Rs.
80750/ton.

Rs in Lacs 339 686

3 Difference in Steel Cost Rs in Lacs 0 347
1.C Cost of Machinery Erection
1 Equipment Erection (Supply Weight) Ton 1150 1380
2 Cost of Machinery Erection @ Rs.
17500/ton.

Rs in Lacs 201 242

3 Difference in Steel Cost Rs in Lacs 0 40
1.D Total Capital Cost Difference
(A3+B3+C3)

Rs in Lacs 0 434

1.E Net Impact on Capital Cost Rs in Lacs 0 434
II) Operating Cost
2.A Power Cost
1 Specific Power Consumption ( Total
of battery Limit)

kWh/Ton 9.4 11.7

2 Total cost of power per annum @ 600
TPH @ 4 Rs./kwh

Rs in Lacs/
Annum

1563 1946


3 Impact due to SPC (Annually) Rs in Lacs 0 383