Appendix A 239

Table A-8. The decision alternatives with constraints imposed

Accept A only OK
Accept B only infeasible, B contingent on C
Accept C only OK
Accept D only OK


Accept A and B only infeasible, B contingent on C
Accept A and C only OK
Accept A and D only OK
Accept B and C only infeasible, capital rationing
Accept B and D only infeasible, B contingent on C
Accept C and D only OK


Accept A, B, and C only infeasible, capital rationing
Accept A, B, and D only infeasible, B contingent on C
Accept A, C, and D only infeasible, capital rationing
Accept B, C, and D only infeasible, capital rationing


Do Everything infeasible, capital rationing


null OK


Table A-9. The decision alternatives cash flows

yr \ Alt A only C only D only A&C A&D C&D null

0 -1000 -400 -500 -1400 -1500 -900 0

1 600 120 290 720 890 410 0

2 600 120 290 720 890 410 0

3 600 120 290 720 890 410 0

4 600 120 290 720 890 410 0