pre-retrofit and post-retrofit periods. Only partial measurement is used
under Option A, with some parameter(s) being stipulated rather than
measured. However such stipulation can only be made where it can be
shown that the combined impact of the plausible errors from all such
stipulations will not significantly affect overall reported savings.


Table A-1. Overview of M&V Options