Managing Information Technology

(Frankie) #1

620 Part IV • The Information Management System


1.No unplanned interruptions
2.Meet scheduled dates
3.Meet budget
4.Continuity of staffing
5.Knowledge transfer
6.Maintain data integrity
7.Resulting service levels will be consistent, with contractual
agreements met
8.Successful integration of application and infrastructure
teams

office was ready to manage this integration. They
were very impressed with the size of Eagle II and
how we handled risk management, change manage-
ment, and progress stewardship.
—Cheri E. Dayton, Senior Manager, Guarantee
Systems Development

Oversight for the integration activities for the merger
as a whole was provided by Rob Autor, who was Sallie
Mae’s VP for integration. Autor and his group of three
global project managers, based in Reston, monitored
the data-center move from a business perspective, keeping
the key players (the board, CEO, McKinsey, institutional
clients, and auditors) informed of the DCR team’s progress.
Under the authority of the larger project office, the
focused project-management office (FPMO) for the DCR
initiative was responsible for monitoring and reporting
global issues related to the data-center integration, includ-
ing status of project plans, timing, codependencies, risks,
and financial issues. The criteria for success for the DCR
project are presented in Exhibit 5.
The project leader for the DCR team was John
Bennett, who had started as a Unity programmer at USA
Group 15 years earlier. Bennett had overall accountability
for planning, management, and communications. One


member of the IT consulting team was kept on the project
full time to help infuse best industry practices and to serve
as a coach. During the kickoff meeting in Reston, Bennett
had seen this particular consultant in action and liked his
strong collaboration and communication skills, strong
work ethic, and willingness to listen.

Defining and Implementing by Move Element
Based on guidelines from both the steering committee and
the project manager, the other managers on the DCR team
were responsible for specific deliverables from each phase.

Phase I
High-Level
Planning

Phase II
Detail Planning

Phase III
Execute

High-Level
Transition
Planning
Sessions

2.1–2.4
Assess
Environment


  • Technical Overview

  • Technical Support
    Assessment

  • Existing Disaster
    Recovery Plans

  • Other App Info


3.1
Define Move
Requirements


  • Move Plan (by Move
    Element)–Overview,
    Move Strategy,
    Target Configuration


3.2
Detailed
Planning


  • Move Plan (Final)

  • Project Plan (Robust)


3.4
Move
Execution


  • Successful


3.5
Post-Move
Execution


  • Clean up


Work Project Manager Meetings

Project Manager Meetings

2.5 –2.6
Define Move
Elements


  • Move Element
    Definition Meetings

  • Move Plan (Move
    Element List)


Revised 12-27-00

3.3
Pre-Move
Execution








  • Service Contracts


TestPlans
Dry-Run
Nesting
Environment
Established

EXHIBIT 6 Data Center Relocation Approach


EXHIBIT 5 Success Criteria for Data Center Relocation
Free download pdf