Architectural Design

(singke) #1
1st ProofTitle: BA: Architectural Design
Job No: PD0710-67/4028

Chapter 3 final (3.5)_.qxd:layouts to chapter one 7/24/10 12:24 PM Page 160


Construction and occupation

The design project

What can be gained by not tying a design up too tightly?
Steve Tompkins
Often things will happen on site that were unintended,
which, because of the methodology and the construction,
we were able to commandeer into the finished language of
the building; that sort of forgiving aesthetic. It not only means
that the finished building is interesting and perhaps more
humane but also that it can carry on moving, albeit in slow
motion, throughout its life. They are able to accrete change
in a way that doesn’t feel threatening.
Graham Haworth
The areas we do leave open to change are really carefully
controlled. For the Young Vic the contract was to finish the
building to within about 95 per cent of the completion in
conventional terms and then for the contract to stop, which
would mean that the theatre production team could move in,
having fitted out the carpentry workshop. We knew that we
had the technical capabilities on site within the client body to
make that perfectly possible and as a deliberate by-product
of that, it meant that the building was owned and absorbed
into the creative organisation and they weren’t frightened of
changes. So you almost gave them permission to take the
building on and kick it around, because that’s what it’s for.
Do you use sample panels to help make decisions about
materiality before work starts on site?
Graham Haworth
You need to know what you’re getting before you get on site,
so the Young Vic panels for example [hand-painted by artist-
collaborator Clem Crosby] were mocked up in the studio
at first. Most of our projects have a warehouse somewhere
with big things in them six months before they’re needed.
There’s one at the moment for the London Library, which has
got the Art Room steelwork in it. We’ve been fiddling with
that for the past six months. So one-to-one mock-ups are
really essential to us.

Project: Snape Maltings
Location: Aldeburgh, UK
Architect: Haworth Tompkins
Date: 2009
above right:
Foyer to performance spaces. The
architects’ choice of materials makes
the difference between original fabric
and new insertions very legible.
below right:
Britten Hall. Acoustic testing in the
new hall following construction.

Text
1st ProofTitle: BA: Architectural Design
Job No: PD0710-67/4028

Chapter 3 final (3.5)_.qxd:layouts to chapter one 7/24/10 12:25 PM Page 160

Free download pdf