Types of pile 31
Timber bearers should be placed between the piles in the stacks to allow air to circulate
around them. They should be protected against too-rapid drying in hot weather by covering
the stack with a tarpaulin or polyethylene sheeting. Care must be taken to place the bearers
only at the lifting positions. If they are misplaced there could be a risk of excessive bending
stresses developing and cracking occurring, as shown in Figure 2.12.
Prestressed concrete piles of hollow cylindrical section are manufactured by centrifugal
spinning in diameters ranging from 400 to 1800 mm in lengths up to 40 m.
The precautions for driving precast concrete piles are described in Section 3.4.2, and the
procedures for bonding piles to caps and ground beams and lengthening piles are described
in Sections 7.6 and 7.7.
One of the principal problems associated with precast concrete piles is unseen breakage
due to hard driving conditions. These conditions are experienced in Sweden where the
widely used jointed or unjointed precast concrete piles are driven through soft or loose soils
onto hard rock. On some sites the rock surface may slope steeply, causing the piles to deviate
from a true line and break into short sections near the toe. Accumulations of boulders over
bedrock can also cause the piles to be deflected with consequent breakage. Because of these
experiences the Swedish piling code recommended the provision of a central inspection hole
in test piles and sometimes in a proportion of the working piles. A check for deviation of the
pile from line can be made by lowering a steel tube down the hole. If the tube can be lowered
to the bottom of the hole under its own weight the pile should not be bent to a radius which
would impair its structural integrity. If the tube jams in the hole, it is the usual practice to
bring an inclinometer to the site to record the actual deviation, and hence to decide whether
or not the pile should be rejected and replaced. The testing tube also detects deviations in
the position or alignment of a jointed pile.
Breakages are due either to tensile forces caused by driving with too light a hammer in
soft or loose soils, or to compressive forces caused by driving with too great a hammer drop
on to a pile seated on a hard stratum; in both cases the damage occurs in the buried portion
of the pile. In the case of compression failure it occurs by crushing or splitting near the pile toe.
Such damage is not indicated by any form of cracking in the undriven portion of the pile above
ground level. The provision of a central test hole will again enable crushing of the pile due
to failure in compression to be detected.
2.2.3 Jointed precast concrete piles
The disadvantages of having to adjust the lengths of precast concrete piles either by cutting
off the surplus or casting on additional lengths to accommodate variations in the depth to a
Cracks in pile due to excessive
bending stresses
Correctly placed
Lifting holes bearers
Misplaced bearers
Figure 2.12Misplaced packing in stacks of precast concrete piles.