conditions where a sufficient period of time is available for the concrete to set before the
bottom of the box is submerged. Arrangements should be made to flood the box to equalize
pressures above and below the seal until the concrete has hardened (Figure 9.28b).
Where piers are located in deep water and there is a risk of ship collision it is desirable to
construct the pile cap at bed level in order to eliminate any unsupported length of piling.
This arrangement is also desirable if lateral forces from earthquakes are transmitted from
the bridge superstructure and piers on to the piles. The pier and pile cap can be constructed


470 Miscellaneous piling problems


Figure 9.28Construction of submerged pile caps (a) In cofferdam (b) In open-topped box.


Pier

Pile cap

Sheet piles
High water

Low water
River bed

Impervious
stratum forming
cut-off for sheet piles

Precast concrete box

Pier
Concrete infill
High water

Low water

Collar

River bed

Rubber seal
to opening

(a) (b)

Figure 9.27Fender beam and piles protecting the river piers of the Sungei Perak Bridge, Malaysia
(after Stanley(9.36)).


1 800 mm OD tubular
steel piles supporting
fender beam

1 500 mm OD
tubular steel
piles

Trough-section
RC fender beam

Pile cap supporting
bridge pier

Riverflow (tidal)