Hydraulic Structures: Fourth Edition

(Amelia) #1

Worked Example 12.4


In a pumped-storage hydropower project, water is delivered from the upper
impounding reservoir through a low-pressure tunnel and four high-pressure
penstocks to the four pump–turbine units. The elevation of the impounding
reservoir water level is 500 m AOD, and the elevation of the downstream
reservoir water level is 200 m AOD. The maximum reservoir storage which
can be utilized continuously for a period of 48 h is 15 106 m^3.
The low-pressure tunnel is constructed as follows: length4 km; dia-
meter8 m; friction factor, 0.028.
The high-pressure penstocks (4 nos.) are constructed as follows:
length of each penstock500 m; diameter2 m, friction factor, 0.016;
turbine efficiency when generating90%; generator efficiency (16 poles,
50 Hz)90%, turbine efficiency when pumping80%; barometric pres-
sure10.3 m of water; Thoma’s cavitation coefficient, 0.043(Ns/100)^2.



  1. Determine the maximum power output from the installation.

  2. Estimate the specific speed and specify the type of turbine.

  3. Determine the safe turbine setting relative to the downstream reser-
    voir water level.

  4. If a simple surge chamber 6 m in diameter is provided at the end of
    the low-pressure tunnel, estimate


(a) the maximum upsurge and downsurge in the surge chamber for
a sudden rejection of one unit and
(b) the maximum downsurge for a sudden demand of one unit.

Solution


The discharge available 15  106 /(48 60 60)86.8 m^3 s^1. The power
output is calculated as follows:


velocity in tunnel86.8/((π/4)88)1.73 m s^1.

Therefore


head loss in tunnelLV^2 /2gD2.13 m,

discharge per penstock86.8/421.7 m^3 s^1 ,

velocity in penstock21.7/((π/4)22)6.91 m s^1.

Therefore


head loss in penstockLV^2 /2gD9.73 m,

gross head at turbine 500200 300 m,

WORKED EXAMPLES 539

Free download pdf