Engineering Economic Analysis

(Chris Devlin) #1
158 PRESENTWORTH ANALYSIS

Multiple Alternatives

So far the discussion has been based on examples with only two alternatives.But multipll
alternative problems may be solved by exactly the same methods employed for problen
with two alternatives. (The only reason for avoiding multiple alternatives was to simpli1
the examples.) Examples 5-8 and 5-9 have multiple alternatives.

A contractor has been awarded the contract to construct a 6-mile-Iong tunnel in the mountains.
During the 5-year construction period, the contractor will need water from a nearby stream. He
will construct a pipeline to convey the water to the main construction yard. An analysis of costs
for various pipe sizes is as follows:

PipeSizes (in.)
2 3 4 6

Installed cost of pipeline and pump
Cost per hour for pumping

$22,000
$1.20

$23,000
$0.65

$25,000
$0.50

$30,000
$0.40

The pipe and pump will have a salvage value at the end of 5 years, equal to the cost to remove
them. The pump will operate 2000 hours per year. The lowest interest rate at which the contractor
is willing to invest money is 7%. (The minimum required interest rate for investedmoney is called
theminimum attractive rate of return,or MARR.) Select the alternative with the least present
worth of cost.

SdllJTI ON-,. -.'.. .-.'.' ....


We can comptite the present worth of cost for each alternative. For each pipe size, the present
worth of cost is equal to the installed cost of the pipeline and pump plus the present worth of
5 years of pumping costs.

PipeSize (in.)

2 6

II~I

Installed cost of pipeline and pump
1.20 x 2000 hr x(P/A,7%, 5)
0.65 x 2000 hr x4.100
0.50 x 2000 hr x 4.100
0.40 x 2000 hr x 4.100
Present worth of cost

$22,000
9,840

$30,000

3,280;
$31,840 $33,280

Select the 3 in. pipe size.

- .. :=;~- =.=

,
IiIooL_ _____

--
r



Free download pdf