Handbook of Civil Engineering Calculations

(singke) #1

  1. Construct the network for the project. Fig. 15
    The network is a delineation of the sequence in which the activities are to be performed.
    Each activity is represented by a horizontal arrow, which may or may not be to scale. The
    arrow representing a given activity is placed to the right of its immediate predecessor ac-
    tivity. Where there are multiple predecessors or successors, broken arrows are used to
    transfer from one activity to another. The duration of each activity is recorded under its
    corresponding arrow.
    Completion of an activity and the start of its successor constitute an event. Com-
    mencement of a given activity is termed its i event; completion of an activity is termed its
    j event. A number is assigned to each event and is recorded in the network in a circle be-
    tween consecutive arrows. Each activity is identified by the events it separates. For in-
    stance, 6-7 designates erect water tank. A chain of activities extending from inception to
    completion of the project is termed a path. In this project there are the following five
    paths:


0-1-2-3-4-5-8-13

0-1-2-3-6-7-8-13

0-1-2-3-9-11-12-13

Legend:
Late event time
Early event time

FIGURE 15. CPM network for site-preparation project.

Install overhead pole line

Pull in
power
feeder

Install
manholes


  • Install
    electrical
    duct bank


Excavate for
electrical
manholes

Install sewer
and backfill

Excavate
for sewer

Rough
grade

Survey
and
lay out

Clear
site

Water-tank
foundations

Erect
water tank

Tank piping
and valvesi

Connect
piping

!Underground
water piping/

Install
Drill well well pump
Free download pdf