Project Management

(Chris Devlin) #1
170 Project Management

and analyze your position—in each of these areas.
Analyzing the Schedule
Schedule analysis relies heavily upon graphic techniques.
Figure 9-3 shows a basic project control schedule, where three
characteristics are displayed for each activity: the original base-
line plan, the amount of progress made, and the forecasted
time-to-complete.
The specific configuration of position and shading illustrated
in this figure would have been determined by input gathered at
a team meeting. Figure 9-4 displays the type of information that

Figure 9-2. Project management do’s and don’ts

Activ.
No.


Activ.
Name
1
2 B
3
4
5

A

C
D
E

6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21

Today’s Date
(Date of team meeting)

July August September

Key
Baseline Plan
Actual
Current Forecast
Critical Path

Figure 9-3. The do’s and don’ts of getting high quality data

•DOreward people for following appropriate processes, even if their
results are not always favorable.


  • DON’Tshoot the messenger of unfavorable information, even if the mes-
    senger is responsible.
    •DOencourage and support an “early warning” mentality in reporting.

  • DON’Tspend any time placing blame when poor results are reported.
    •DOimmediately move into a mode of collaborative problem-solving when
    problems surface.

  • DON’Tever play one team member against another, or criticize one
    team member while talking to another.
    •DOdemonstrate personal commitment and accountability.

Free download pdf