Project Management

(Chris Devlin) #1
Maintaining Control During Project Execution 171

task performers would have provided, to arrive at the control
schedule shown in Figure 9-3.
Recording and displaying the information you receive from
task performers is little more than “plugging in” status infor-
mation. This simple and straightforward method will prob-
ably be adequate for
many projects.
Interpreting control
schedules is also straight-
forward—if they’re proper-
ly constructed. An analysis
of Figure 9-4 allows us to
make several observations
about the past perform-
ance and current status of
every activity shown on
this control schedule. For
example:



  • Activity A started and finished on time.

  • Activity B started on time and has taken longer than
    expected.

  • Activity C started two weeks late and the duration hasn’t
    changed.


Activ.
No.

Activ.
Name
1
2 B
3
4
5

A

C
D
E

6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21

Today’s Date
(Date of team meeting)

July August September

“I have a couple of days left.”
“I’ll be done in one week.”
“I have two weeks
work left to do.”
“I can do this in two
weeks, not three.”

Figure 9-4. Information to develop control schedule


“Decorating” Your
Schedule
When it comes to choosing
schedule graphics, there really aren’t
any standards for coloring, shading, or
patterns; you can choose any scheme
that suits you. Most scheduling soft-
ware applications allow you to select
from a large menu of choices for color
or shading. Just be sure your choice of
colors and patterns is not distracting!
Free download pdf