SECTION 07550

MODIFIED BITUMEN MEMBRANE ROOFING (SBS)

Modified Bitumen Membrane Roofing (SBS)
UIHC #20X-0XX 07550-4

1.06 QUALIFICATIONS

A. Applicator:


  1. Company specializing in performing the work of this section with a minimum of five
    (5) years documented experience.

  2. Company certified by the membrane manufacturer for a minimum of three (3) years as
    an approved applicator of the products specified in this section.

  3. Company having workmen trained by the membrane manufacturer. These trained
    workmen shall perform the work.


1.07 DELIVERY, STORAGE AND HANDLING


A. Deliver and store materials under provisions of Section 01610.

B. Deliver materials in sufficient quantity to allow continuity of work.

C. Coordinate delivery of materials with Owner so that minimal interruption of Owner's
operations occurs.

D. Materials shall be stored in their original, tightly sealed containers or unopened packages, and
shall be clearly labeled with the manufacturer's brand name and such identifying reference
numbers as are appropriate. Deliver materials to job site on pallets. Do not stack pallets.

E. Materials shall be stored in a neat, safe manner, so as not to exceed allowable live load of the
storage area. Contractor shall not load pallets of material onto the roof deck without approval
from the Architect/Engineer prior to loading. Disperse materials on roof deck to avoid
concentrated loading.

F. Store materials in dry, protected areas in an upright position. Control temperature of storage
areas in accordance with manufacturer's instruction. Protect materials from freezing.

G. Follow manufacturer's guidelines for required temperatures of material prior to application.

H. Any materials damaged in handling or storage are not to be used.

I. The Contractor shall assume full responsibility for the protection and safekeeping of materials
stored on Owner's premises.

J. Store roll goods on ends only. Discard rolls which have been flattened, creased, or otherwise
damaged.

K. Remove wet material from project site.

L. Comply with fire and safety regulations.

November 1, 2016