Construction-Phase Process


  1. Installing C ontractor prepa res roofing and roof related sheet metal submittals, FM
    Global Roof Nav "Contractor Package" for each assembly, and preliminary F M Global Form X -2688 –
    Application for Acceptance of Roofing System for e ach assembly, and submits to the Design Professional for
    review. This submittal package s hall demonstrate that all aspects of the r oo f system a nd roof related sheet metal
    work comply with the specifications and represent combinations of products that c omply with the specified
    RoofNav Assembly Numbers.

  2. Roofing manufacturer and Design Prof essional assist Contractor with thi s submittal, as necessary. Review and
    revisions s hall proceed until the submittal i s judged to be capable of passing FM Global review and approv al.

  3. Contractor then transmits roofing and roof r elated sheet metal submitta ls, F M Global
    RoofNav "Contractor Package" f or each assembly, and FM Global Form X -2688 – Application f or Acceptance of
    Roof ing System for e ach assembly to FM G lobal for review and approv al.
    FM Global reviews and provides comments. If all of the prior s teps have been completed satisfactorily, FM Global
    app roval should be a tur nkey process. This step, in conjunction with final field review, will provide the for mal
    acceptance for the r oof s ystem.