ACTUAL BUILDING
WORKExcavation, preliminary work 302,600Foundations 554,545Reinforced concrete frame 2,799,775Bricklaying 2,393,836Staircases 178,498Roofing, insulation 372,800Windows and doors 1,586,350Piping work 4,008,700Rendering 579,955Construction drying 169,000Floors 1,015,880Painting 720,000Façade work 522,815Specialist interior work 88,430Machine installation (kitchen, laundry, bakery, etc.), fireplaces 795,840Management 1,765,000TOTAL [FIM] 17,854,024
INSTALLATIONS,
OUTDOOR AREAS
AND INTERIORSInstallations (electricity, low-current, specialist heating
systems, wastewater treatment)1,392,000
Interior work 863,950Materials 657,650Medical technology 587,500Outdoor areas 231,500TOTAL [FIM] 3,732,600
TOTAL
Construction work proper 17,854,024Installations, outdoor areas and interiors 3,732,600Other 313,376TOTAL [FIM] 21,900,000
SUMMARY OF BUILDINGS COSTS
630630 Cost estimate, December 1, 1929. (PSA).Table 3.2.1b. Cost estimate 1929.