paimio sanatorium

(Jacob Rumans) #1
ACTUAL BUILDING
WORK

Excavation, preliminary work 302,600

Foundations 554,545

Reinforced concrete frame 2,799,775

Bricklaying 2,393,836

Staircases 178,498

Roofing, insulation 372,800

Windows and doors 1,586,350

Piping work 4,008,700

Rendering 579,955

Construction drying 169,000

Floors 1,015,880

Painting 720,000

Façade work 522,815

Specialist interior work 88,430

Machine installation (kitchen, laundry, bakery, etc.), fireplaces 795,840

Management 1,765,000

TOTAL [FIM] 17,854,024

INSTALLATIONS,
OUTDOOR AREAS
AND INTERIORS

Installations (electricity, low-current, specialist heating
systems, wastewater treatment)

1,392,000

Interior work 863,950

Materials 657,650

Medical technology 587,500

Outdoor areas 231,500

TOTAL [FIM] 3,732,600

TOTAL


Construction work proper 17,854,024

Installations, outdoor areas and interiors 3,732,600

Other 313,376

TOTAL [FIM] 21,900,000

SUMMARY OF BUILDINGS COSTS


630

630 Cost estimate, December 1, 1929. (PSA).

Table 3.2.1b. Cost estimate 1929.