The Internet Encyclopedia (Volume 3)

(coco) #1

P1: IML/FFX P2: IML/FFX QC: IML/FFX T1: IML


ProjectMngmtTechn WL040/Bidgolio-Vol I WL040-Sample.cls June 19, 2003 16:49 Char Count= 0


PROJECTSCHEDULINGTOOLS ANDTECHNIQUES 117

Figure 10: Gantt chart for software launch project in Microsoft Project.

float. Slack or float is the amount of time an activity may
be delayed without delaying a succeeding activity or the
project finish date.
To find the critical path for a project, a project manager
should first develop a good network diagram, which, in
turn, requires a good activity list based on the WBS. Once
a project network diagram has been created, the manager
must also estimate the duration of each activity to de-
termine the critical path. Calculating the critical path in-
volves adding the durations for all activities on each path
through the project network diagram. The longest path is
the critical path.
Figure 11 provides an example of a project network
diagram using the activity-on-arrow format for simplicity.
Note that each of the four paths starts at the first node
(1) and ends at the last node (8) on this diagram. This
figure also shows the length or total duration of each path
through the project network diagram. These lengths are
computed by adding the durations of each activity on the
path. Because path B-E-H-J at 16 days has the longest
duration, it is the critical path for the project.
Figure 12 shows the network diagram and critical
path when the same project information is entered into
Microsoft Project 2000. This format is called the prece-
dence diagramming method (PDM) and is used by most
software packages. Project management software can
definitely help in creating network diagrams and deter-

mining critical paths and slack amounts for all project
tasks.
What does the critical path really mean? The critical
path shows the shortest time in which a project can be
completed. Even though the critical path is the longest
path, it represents the shortest time it takes to complete
a project. If one or more of the activities on the critical
path takes longer than planned,the whole project schedule

G=6

C=3

Note: Assume all durations are in days.
Path 1: A-D-H-J Length = 1+4+6+3 = 14 days
Path 2: B-E-H-J Length = 2+5+6+3 = 16 days
Path 3: B-F-J Length = 2+4+3 = 9 days
Path 4: C-G-I-J Length = 3+6+2+3 = 14 days

Since the critical path is the longest path through the network diagram, Path 2,
B-E-H-J, is the critical path for Project X.

B=2 F=4 J=3

H=6

I=2

A=1

D=4
E=5

2

(^13)
4
5
6 8
7
Figure 11: Using a project network diagram to determine the
critical path.

Free download pdf