Characteristics of organic wastes 41
stations of the palm oil mills. The characteristics of these wastewaters at 50
percentile values are given in Table 2.12.
Table 2.11 Probability of wastewater flows per ton of FFB processed at different
measuring stations of palm oil mills (Thanh et al. 1980)
Flow in m^3 /ton FFB (m^3 /hour)
Palm oil
mill
Measuring station
(see Figure 2.4)
50
Percentile*
70
Percentile*
80
Percentile*
90
Percentile*
Plant A
(Malaysia)
- Oil clarification
room
1.04(22.0) 1.14(24.8) 1.21(26.5) 1.31(29.0)
- Boiler house and
hydrocyclones
0.49(10.5) 0.57(12.5) 0.62(13.8) 0.70(16.0)
- Sterilizer
building and press
station
0.76(15.8) 0.84(17.5) 0.89(18.8) 0.96(20.6)
- Combined flow
(1+2+3)
2.32(47.0) 2.50 (49.8) 2.60 (51.5) 2.75(54.0)
Plant B
(Malaysia)
- Oil clarification
room
1.25(15.5) 1.50 (18.0) 1.68 (19.5) 1.94(22.0)
- Boiler house,
sterilizer building
and hydrocyclones
1.90(21.0) 2.21(23.7) 2.43(25.7) 2.80(28.5)
- Combined flow
(1+2)
3.23(37.0) 3.72(42.0) 4.10(46.0) 4.60(51.0)
Plant C
(Malaysia)
- Sterilizer
building
0.11(2.2) 0.15(2.7) 0.17(3.1) 0.22(3.8)
- Oil clarification
room
1.30(22.5) 1.60(27.0) 1.83(31.0) 2.21(36.0)
- Boiler house 0.52(8.7) 0.61(10.2) 0.67(11.2) 0.76(13.0)
- Hydrocyclones 0.27(4.7) 0.34(5.9) 0.38(5.8) 0.45(6.5)
- Combined flow
(1+2+3)
2.25(36.0) 2.60(41.5) 2.85(45.0) .25(50.0)
Plant D
(Thailand)
- Oil clarification
room
0.89(6.1) 1.01(8.0) 1.09(9.2) 1.11(11.8)
- Sterilizer
building and oil
clarification room
1.09(8.9) 1.21(10.5) 1.29(12.0) 1.39(13.0)
- Miscellaneous
sources
0.64(4.9) 0.80(5.9) 0.87(6.5) 1.00(7.8)
- Combined flow
(1+2+3)
1.73(13.8) 2.01(16.4) 2.16(18.5) 2.39(20.8)
*If a 50 percentile flow is used in the design of wastewater treatment facility, it means that 50% of
the time the flow of that particular waste stream will be equal or less than the stated figures.