Canal Boat — November 2017

(Marcin) #1
canalboat.co.uk Canal Boat November 2017 63

RESTORATION


The junction bridge still exists, and Canal
Trust volunteers have been at work
removing vegetation from the brickwork,
and re-setting coping stones knocked off
by vandals.
There are plans for more in this area,
where following an unsuccessful Heritage
Lottery Fund bid some years ago, the
advice was to ‘do a small project first’.
So the plan is to dig out and restore the
filled-in first lock: matters have been
delayed complicated by asbestos in the
infill, but investigations have shown that
it is relatively low level contamination.
There are then no major problems with
the first mile (which survives as a path,
and passes under the fine 1930s concrete
Cockayne’s Bridge). The local authorities
are supportive, and the Canal Trust could
take over ownership from the council.
Crossing the M1 (which blocks the
original line) looks tricky, but the Trust
believes that a nearby road bridge is wide
enough to squeeze a canal in as well.
Beyond the motorway there is less to
see, but the course is unobstructed, and
(as with much of the route) possible
marina and development sites have been
identified which could support canal
reinstatement. A footpath follows the
route west past Breaston – where former
canal pub the Navigation survives, and
may one day have a liftbridge alongside it.
A cycleway follows the canal line to
Draycott, site of the next length that’s
looking likely to see work soon. By a
dilapidated old brick building is the start
of what the Trust has dubbed the ‘first
kilometre’. Already partially re-excavated
for drainage purposes, it’s proposed for
reinstatement to navigable dimensions as
the first completed length of the restored
canal. As a major earth-moving exercise

(plus waterproof lining) it’s likely to be a
job for contractors rather than volunteers,
costing around £400,000. The Trust has
already secured £40,000 in pledges
towards a target of £100,000, which it feels
will demonstrate the necessary levels of
support when going for grant funding for
the remainder. If the money can be raised,
DSCT hopes that the work could take
place in either summer 2018 or 2019.
But it’s more than just digging 1km of
ditch. The plan is to include a slipway and
parking, use it to hold trip-boat events,
encourage fishing, and make a community
asset for Draycott. And that’s where the
‘dilapidated old brick building’ mentioned
above comes in...
Built as six canal workers’ cottages,
later used as a silk mill, the building was
vacated in 1985 and fell derelict. It has
now been bought by the Trust, which has
begun renovation with the aim that it will
combine housing for rent (to bring an
income for the Trust) with community
functions including a café and farm shop.
The First Kilometre ends where the
canal passes under the A6005 via another
concrete bridge. A footpath continues to
follow the line of the canal as it passes
through farmland to reach Borrowash,
where we find the next restoration site.
Borrowash Bottom Lock was partially
restored by volunteers some years ago.
The completion of the lock including
repairs to wing walls and reinstatement of
coping stones (plus a length of hedgerow
work) is seen as very much a volunteer
project – although there will be other
work needed including a water supply
from a nearby brook and moving a drain.
Following a well-preserved length
above the lock, the partly infilled canal

route forms a linear park around the
south side of Borrowash, leading to
Spondon, where two surviving bridges


  • a traditional brick arch and a steel beam
    bridge – have already been restored.
    Beyond there, however, things get more
    difficult as the canal approaches Derby.
    Originally it continued west into the city,
    crossing the River Derwent on the level
    before heading south to Swarkestone. But
    with parts of the route on both sides of
    the river having been built on, the Trust
    has gone for a more radical approach.
    A new route is proposed which will cut
    across southwest from west of Spondon,
    bridging the Derwent on a new aqueduct
    alongside an existing railway bridge,
    before continuing south of the river
    (where a new culvert has already been
    built to carry it under Pacific Way) and
    rejoining the southern length of the canal.
    (Until it’s built, those following the route
    on foot will need to take the footpath
    alongside the A5111, then take the
    riverside path westwards before turning
    left following the signs to Swarkestone.)
    Having rejoined the original route south
    of the Derwent, there is a footpath and
    cycleway following the line all the way to
    the Trent & Mersey at Swarkestone –
    including three surviving bridges and


The ‘First Kilometre’ length at Draycott


Volunteer project: the part-restored Borrowash Lock

Surviving bridge and lock south of Derby
Free download pdf