Airforces

(Steven Felgate) #1
http://www.airforcesmonthly.com #359 FEBRUARY 2018 // 77

Export success


suit in March 2006. While the first pair was
funded by Yakovlev, funding for ‘03’ came
from the Russian defence ministry. The
subsequent flight-test effort proved rather
problematic and ‘03’ was lost due to an FBW
failure in July 2006. Then, another aircraft
destined for joint state testing, appropriately
serialled ‘04’, was built to replace ‘03’ and
was reported delivered in June 2009.
An initial batch of 12 Yak-130s was ordered
as early as 2006. The ‘preliminary conclusion’
of the suitability testing was issued by the
929th State Flight Test Centre in Akhtubinsk
in 2007 and opened the door for large-scale
production. Two Yak-130s were completed
in 2009 and a further nine in 2010. However,
entry into service proved a protracted affair.

In April 2009, the state testing programme
with a basic set of weapons was reported
completed, and in December of the same
year the effort with an expanded weapons
selection was said to have ended. The first
batch of four production-standard Yak-
130s was delivered to the combat training
centre in Lipetsk in February 2010 to start
instructor training, while the first batch of
aircraft for the Borisoglebsk training centre
followed in April 2011. The first training
flights for instructors converting to the Yak at
the 209th Training Aviation Regiment (UAB)
in Borisoglebsk were performed in August
of that year. Follow-on Yak-130s, newly
delivered from Irkut, joined flight operations
with the 209th UAB in mid-November 2013.

The Rosoboronexport-led Yak-130 sales campaign
has yielded some success. The first export order
was placed by Algeria in 2006, calling for 16 aircraft
from Irkut. Completion of the order was delayed
amid flight control revisions after the various crashes,
combined with the protracted establishment of the
production line at the IAZ plant in Irkutsk. All the
aircraft, which were originally scheduled for delivery
in 2008 and 2009, were handed over in 2011. In
2010, Libya placed an order for six Yak-130s but they
were never delivered due to the civil war. A deal for
36 aircraft was signed with Syria in December 2011.
This was similarly put on hold. The export sales
drive gained momentum after 2010, with three more
customers in the shape of Belarus, Bangladesh and
Myanmar placing orders between 2014 and 2016.
Irkut maintains that the Yak-130’s price
is significantly lower than that of any other
advanced jet trainer. At the same time the life-
cycle costs are advertised as four to six times
lower than those of the Su-27 and MiG-29.
Belarus ordered eight Yak-130s in identical
configuration to the VKS aircraft in December 2012;
four were taken on strength in April 2015 and four
more followed in December 2016. Belarus has already
explored the full combat capabilities of the Yak-130,
including launches of R-73 missiles against parachute
targets and drops of live KAB-500Kr TV-guided
bombs. Bangladesh became the third customer,
with an order for 16 jets, all of which were delivered
by the end of 2016 to replace A-5C attack aircraft.
Bangladeshi aircraft serial 102 was lost in a crash on
July 11, 2017, both pilots ejecting safely and another

pair was lost on December 27 (see Attrition, p95).
Myanmar is the latest customer, with a June 2015
order for six aircraft. The first three were delivered
in late 2016 and three more arrived last year. An
additional order has been placed by the same
customer for an undisclosed number of aircraft,
slated for delivery in 2018. The list of prospective
new export customers for the Yak-130 includes
Armenia, Egypt, Kazakhstan, Laos and Vietnam.

A Yak-130 fuselage under construction at the IAZ
plant in Irkutsk. Irkut

The Yak-130 completed its state testing programme
on December 22, 2009, which permitted regular
operation in VKS training units, while the
Lipetsk-based centre was tasked with so-called
experimental operation, together with additional
tests and conversion training of instructor pilots.
Stanislav Bazhenov


Production at the Sokol plant began in late 2008, with initial deliveries to the Russian air arm made in April
2010, when the first four series-standard machines were handed over to the Lipetsk-based combat training
and aircrew conversion centre. Andrey Zinchuk
Free download pdf