FlightCom – August 2019

(singke) #1

25 FlightCom Magazine


doctrinal requirements of the acquisition.
Unlike arms acquisitions elsewhere in
the world, those in South Africa are fixed
cost. That is, once you reach the point of
actually ordering an aircraft, the only thing
that should change are movements owing to
currency. While it’s theoretically possible
to request a higher ceiling, in practice it’s
almost never granted.
In effect DAHB 1000 achieves this
by strictly separating out risk-carrying
portions of an acquisition, such as
developing uncertain new technologies,
from the acquisition itself. These technology
development projects, conducted as part of
the acquisition project, are kept intentionally
small, time boxed, and limited in scope.
As an example, let’s say the SAAF
wanted to acquire a new transport helicopter
but for reasons of national defence policy
and the creation of indigenous capabilities,
it desired to have a new optical distributed
vision system developed by a local
company. That element would then be a
separate technology development project
with a specific time scale designed to
reach maturity just at the point where the
acquisition project reached final approval
on its subsystems. The project officer in
charge of the acquisition project would then
have to ensure that there was a fallback plan
to use other available systems to meet the
operational requirement should the attempt
to develop and industrialise the technology
fail to deliver.
Virtually every contract also includes
strong penalty clauses for late delivery or
failure to meet specifications, which can
be done purely because DAHB 1000 sets
high standards for the requirements and
specification analysis phases, as well as the
verification phase. Meaning that there’s an
objective and difficult to contest basis on
which to hold suppliers to account.
Even the ‘Arms Deal’, with its
controversy over selections, at least
delivered good prices and was run on
time and on budget because despite there
being a custom (and flawed) initiation
process, Armscor and the DOD used the
then VB1000 to guide the negotiation and
contract stage, and kept each contract to its
cost ceiling. This is why the SAAF had to
cancel two Gripens in order to afford extra
capability that it decided it wanted late in
the process.

Since then most of the gaps in policy
that led to the deviations from VB1000 in
the Arms Deal have been plugged, while the
regulations around both national industrial
and defence industrial offsets have been
improved substantially. It’s also notable that
winning bids are not chosen on price alone,
but on a complex process of measured
factors including the benefit to local
industry, supportability and logistics, and so
on, with price being the strongest variable.
Of course, no system is entirely perfect.
For one, efficiently running a process as
complex as this requires a large number
of exceptionally skilled people as project
officers and other roles. But the severe
budget crunch the SANDF, and the SAAF
in particular, have faced over the past
decade has meant that very few large scale

acquisitions have been carried out, so the
process is not tested as often as it ideally
should be.
Transparency is also lacking, as while
DAHB 1000 specifies that Parliament’s
portfolio committee on defence should
be briefed bi-annually on all cardinal
acquisition projects, no such briefings have
taken place. And its sheer rigidity means it
takes a long time for a project to go from
a Required Operational Capability to an
acquisition if the various control boards
aren’t meeting frequently. In practice, this
has meant that in a number of cases a project
has taken so long to get all the necessary
approvals that by the time it’s ready either
the market or the strategic situation has

changed. Also currency movements mean
the original approved budget no longer
suffices and the process must start all over
again as each approval only has a limited
lifespan.
These can all be solved. For one, DAHB
1000 does contain a procedure for expedited
urgent operational requirements, which
follow a much shorter process but with the
highest levels of authorisation required.
The delays in receiving approvals from the
various steering committees and boards
is simply bad management and should not
happen to the extent it does.
However, that all assumes that the
SDA remains available for the DOD to use,
because it certainly will not have enough
time to both alter its policies and accounting
practices, and change its Financial

Management System in time to be able to
cope with the planned phasing out.
It also assumes that there will be at least
some acquisition funding, but the medium
term budget proposals from National
Treasury show the SANDF’s budget being
cut again and again, reducing the acquisition
budget to almost nothing.
Without the ability to buy anything at
all, the question of how that buying should
be done becomes merely academic.

ABOVE: It took a lot to subvert the arms
deal - and will require even more now.

.


.


.

Free download pdf