PROJECT FOCUS
oilandgasmiddleeast.com AUGUST 2019
Rabab Harweel Integrated Project (RHIP)
involves the construction of a new inte-
grated oil and sour gas facility, utilising gas
from the Rabab field to allow Miscible Gas
Injection within the Harweel oil reser-
voirs to maximise recovery. Harweel field
includes 240 million barrels of oil and 100
million barrels of condensate while export-
ing 1 trillion cubic feet of non-associated
gas when production starts in 2019. When
complete, the facility will deliver: - 6 MM
SCMD of sweet gas - 60,000 BPD of oil - 16
MM SCMD of high pressure sour injection
BACKGROUND PROJECT SCOPE (INCOMPLETE)
Date Status
Jul 2019 Gas production commences from the fi rst sour wells (two months ahead of schedule).
Mar 2019 Construction of central processing facility (CPF)is complete. Works to connect the CPF to the production wells is underway.
May 2018 Al Hassan's work on the Rabab Harweel project is now 98% complete.
Feb 2018 The project is well ahead of plan and budget with completion rate of 90%. Operations are expected to start in July 2019.
Jul 2017 Engineering is complete, and procurement is 93% complete. Project milestones achieved include: Fabrication of 29,000 tonnes of on the fabrication of 800,000 inch of piping; Installation of 67 pre-assembled rack (PAR). structural steel; 90% completion
Jun 2017 CCC awards Al Nahdha Group a $4.25mn contract for supply and installation of fi reproofi ng materials on structures and equipment.
May 2017 Construction of the RHIP plant is taking shape. The majority of process equipment are being delivered. Most associated buildings have been completed.
Mar 2017 Kentz Overseas wins a fi ve-year commissioning support services framework contract to provide systems completions, commissioning and start-up service activities.
Feb 2017 Procurement and engineering works are 80% complete. Construction is going as per schedule.
Jun 2016 PDO obtains a syndicated loan from international banks to support the fi nancing of the development of Rabab Harweel project.
Mar 2016 Petrofac awards Veolia a contract to provide process water treatment solutions. Veolia will support the engineering and supply of water treatment systems.
Feb 2016 RHIB is progressing well with about 5% of the project being completed. Work on the power plant is advanced, so are the foundations and the wells.
Oct 2015 CCC completes its scope of work.
Aug 2015 Consolidated Contractors Company (CCC) wins civil works package. Oman Drydock Company obtains a $10mn contract to provide CCC with super steel structures.
Jul 2015 MAN Diesel & Turbo (MDT) wins contract to deliver eight compressor trains. OHI Petroleum and Energy Services is MDT’s local ageand two low-pressure compressor trains for acid gas application, one high- and one low-pressure compressor train for fl ash gas application and two trains for export.nt. MDT’s order comprises two high-
Feb 2015 Al Hassan Engineering awards Anewa contract for Plant Design Management System 3D Modeling services for GTG & HRSG OEM packages and CCWS system for PDO.
Oct 2014 EagleBurgmann Middle East has been chosen to provide sealing solutions for PDO’s RHIP project.
Mar 2014 PDO made the FID on the project. PDO awards Al Hassan Engineering Company EPC contract for the Rabab Harweel Power Plant & HRSG$1bn contract, will provide detailed engineering and construction and commissioning management services on the integrated oil and sour gas facility. Project (RHIP). Petrofac wins
Jul 2013 The technical proposals for the EPC contract have been submitted by fi ve contractors.
Apr 2013 FEED study is complete. PDO issues invitation to bid for the EPC contract. 6 contractors have been pre-qualifi ed to bid for the EPC contract.
Jul 2012 FEED is set to fi nish in Q3 2012. The FID will occur in Q2 2013. The main contract will be awarded in Q3 2013. The project should be on-stream by Q3 2017.
2011 The Front-End Engineering Design (FEED) works have started. The FEED will be done in-house with WorleyParsons.
Facilities with intake
capacity of 15 MMSm3/d
MGI in Harweel fields
Wells hook up: 69 wells (30
producers, 39 injectors)
New gathering systems for
Rabab, Rabab SE & Ghafeer
Oilfield flows through
existing gathering systems
to Harweel 2AB
Sour gas treatment
400 t/d LPG production
(prod) station
Condensate prod station
Harweel oil prod through
Harweel 2AB
Interconnection between
Harweel 2AB & new station
Wellpad piping
GRE flowlines
Remote gathering manifold
stations
Condensate separation and
stabilisation train
Flash gas booster
compression train
Gas treatment: 2-3 GSU
trains & mole sieves units
2 sweet gas export
compression trains
2 acid gas compression
trains
3 gas injection
compression trains
Gas export pipeline
Condensate export pipeline