GCC OIL – AUGUST 2019
Project Country City Sector Facility Budget Award Date Status Completion Date
ADNOC & Al Yasat Petroleum- Bu Haseer Field Development Package 2 & 3 U.A.E. Abu Dhabi Oil, Offshore Oil Field Development 300,000,000 2018-Q2 Engineering & Procurement 2025-Q4
ADNOC & EMARAT - Fujairah Terminal Expansion Phase 3 U.A.E. Fujairah Oil Oil Storage Tanks 40,000,000 2019-Q2 On Hold 2020-Q1
ADNOC - Haliba Oil Field - Phase 1 U.A.E. Abu Dhabi Oil Oil Field Development 500,000,000 2018-Q1 Commissioning 2019-Q4
ADNOC - Replacement of Flowflines & Wellheads Installation - Overview U.A.E. Abu Dhabi Oil, Pipeline Oil & Gas Field 150,000,000 2019-Q3 EPC ITB 2021-Q1
ADNOC Distribution - Bateen Executive Airport- Jet Fuel Depot U.A.E. Abu Dhabi Oil Oil Storage Tanks 80,000,000 2017-Q2 Commissioning 2 019-Q4
ADNOC Gas Processing- Integrated Gas Development (IGD) - Expansion (Onshore Pipeline) U.A.E. Abu Dhabi Oil, Gas Gas Production 710,000,000 2014-Q4 Commissioning 2019-Q3
ADNOC Offshore - Bu Haseer Field U.A.E. Abu Dhabi Oil, Pipeline Pipeline 155,000,000 2016-Q2 Construction 2019-Q4
ADNOC Offshore - Lower Zakum - Oil Lines Replacement (Phase 1) U.A.E. Abu Dhabi Oil, Pipeline Pipeline 850,000,000 2014-Q1 Commissioning 2019-Q3
ADNOC Offshore - Nasr Full Field Development - Overview U.A.E. Abu Dhabi Oil, Gas, Offshore Oil Field Development 1,700,000,000 2011-Q4 Construction 2020-Q1
ADNOC Offshore - Nasr Full Field Development - Phase 2 (Package 2 - Platforms) U.A.E. Abu Dhabi Oil Oil Field Development 195,000,000 2014-Q3 Commissioning 2019-Q4
ADNOC Offshore - Nasr Full Field Development - Phase 2 (Package 3) U.A.E. Abu Dhabi Oil Oil Field Development 200,000,000 2015-Q3 Commissioning 2019-Q3
ADNOC Offshore - Umm Al Lulu Field Development - Overview U.A.E. Abu Dhabi Oil Oil Field Development 2,500,000,000 2013-Q2 Commissioning 2019-Q4
ADNOC Offshore - Umm Al Lulu Field Development - Package 2 U.A.E. Abu Dhabi Oil Oil Field Development 1,700,000,000 2013-Q3 Commissioning 2019-Q4
ADNOC Offshore - Umm Shaif Infield Pipelines Replacement U.A.E. Abu Dhabi Oil, Pipeline Oil Field Development 500,000,000 2019-Q3 EPC ITB 2021-Q4
ADNOC Offshore - Upper Zakum Full Field Development - 750 Project - Surface Facilities - EPC 2 U.A.E. Abu Dhabi Oil, Gas Oil Production 3,840,000,000 2013-Q2 Commissioning 2019-Q3
ADNOC Offshore - Zirku Facilities Capacity Enhancement U.A.E. Abu Dhabi Oil Oil Field Development 410,000,000 2018-Q1 Construction 2020-Q4
ADNOC Offshore- 750 West Region- Capacity Expansion & Sulphate Reduction Plant- EPC 3 U.A.E. Abu Dhabi Oil, Gas Sulphur Recovery 300,000,000 2017-Q1 Construction 2019-Q4
ADNOC Offshore- Nasr Full Field Development - Phase 2 (Package 1 - Wellheads and Pipeline) U.A.E. Abu Dhabi Oil Oil Field Development 900,000,000 2014-Q3 Construction 2020-Q1
ADNOC Offshore- Umm Shaif & Zakum - Application of DOF on Brownfield Towers U.A.E. Abu Dhabi Oil, Offshore Oil Field Development 120,000,000 2019-Q3 EPC ITB 2022-Q4
ADNOC Onshore - 1.8MBPD Development - Bab Artificial Lift Wells U.A.E. Abu Dhabi Oil Artificial Lift 100,000,000 2019-Q4 EPC ITB 2021-Q3
ADNOC Onshore - Asab Full Field Development II - Overview U.A.E. Abu Dhabi Oil Oil Field Development 450,000,000 2019-Q1 Engineering & Procurement 2022-Q1
ADNOC Onshore - Asab Full Field Development II - Stage 1 U.A.E. Abu Dhabi Oil Oil Field Development 100,000,000 2019-Q1 Engineering & Procurement 2021-Q4
ADNOC Onshore - Asab Full Field Development II - Stage 2 U.A.E. Abu Dhabi Oil Oil Field Development 350,000,000 2019-Q3 EPC ITB 2022-Q1
ADNOC Onshore - Bab Sustainable Facilities U.A.E. Abu Dhabi Oil Pipeline 250,000,000 2019-Q3 EPC ITB 2020-Q4
ADNOC Onshore - Buhasa Integrated Facilities Project U.A.E. Abu Dhabi Oil Oil Production 3,000,000,000 2018-Q4 Engineering & Procurement 2024-Q1
ADNOC Onshore - Fujairah MOT - Hydraulic Pressure Recovery System Turbine U.A.E. Fujairah Oil Oil Field Development 800,000,000 2019-Q4 On Hold 2023-Q1
ADNOC Onshore - Mender Field Development U.A.E. Abu Dhabi Oil Oil Field Development 350,000,000 2015-Q2 Commissioning 2019-Q4
ADNOC Onshore - North East Bab (NEB) - (Al Dabbiya) ASR U.A.E. Abu Dhabi Oil Oil Production 2,500,000,000 2019-Q4 EPC ITB 2023-Q4
ADNOC Onshore- Bab Integrated Facilities Project U.A.E. Abu Dhabi Oil Oil Field Development 3,000,000,000 2018-Q1 Construction 2020-Q1
ADNOC Onshore- Bab TH-F Peripheral Development U.A.E. Abu Dhabi Oil, Gas Nitrogen 400,000,000 2019-Q3 On Hold 2020-Q4
ADNOC Onshore- Buhasa- Wellhead Automation U.A.E. Abu Dhabi Oil Oil Field Development 100,000,000 2019-Q4 FEED 2023-Q3
ADNOC Onshore- Qusahwira Field Development - Phase 2 U.A.E. Abu Dhabi Oil Oil Field Development 150,000,000 2019-Q2 Construction 2023-Q 3
ADNOC Onshore- Rumaitha, Shanayel and Northeast Bab Tie In U.A.E. Abu Dhabi Oil Oil Field Development 350,000,000 2018-Q4 Construction 2024-Q3
ADNOC Onshore- South East Asset- Tie-in Project (A,B, C & D) U.A.E. Abu Dhabi Oil Oil Field Development 650,000,000 2015-Q3 Engineering & Procurement 2024-Q4
ADNOC Refining - Ruwais Complex Upgrade - New Refinery U.A.E. Abu Dhabi Oil, Petrochemicals Refinery 45,000,000,000 2020-Q1 Pre-FEED 2023-Q1
ADNOC Refining- Ruwais- LPG Recovery U.A.E. Abu Dhabi Oil, Refining Crude Oil Distillation Unit 40,000,000 2019-Q2 EPC ITB 2022-Q1