Estimating in Building Construction

(Kalthiya AryanmXZGQq) #1
Excavation 89

removing fences and rails
removing boulders
wrecking old buildings

Foundations:
underpinning existing buildings
disconnecting existing utilities
clearing shrubbery

Excavation (including backfilling):
basement
footings
foundation walls
sheet piling
pumping
manholes
catch basins
backfilling
tamping (compacting)
blasting
grading (rough and fine)
utility trenches
grading and seeding lawns
trees
shrubbery
topsoil removal
topsoil brought in

9–19 Piles


Piles used to support loads are referred to as bearing piles.
They may be wood, steel “H” sections, poured-in-place con-
crete with metal casing removed, poured-in-place with metal
casing left in place, wood and concrete, or precast concrete.
The wide variations in design, conditions of use, types
of soil, and depth to be driven make accurate cost details dif-
ficult to determine unless the details of each particular job
are known. The various types and shapes available in piles
also add to the difficulty, particularly in concrete piles. It is
suggested that estimators approach subcontractors who spe-
cialize in this type of work until they gain the necessary
experience. Figure 9.42 gives approximate requirements for
labor when placing bearing piles.


Sheet piling may be wood, steel, or concrete. They are
used when the excavation adjoins a property line or when
the soil is not self-supporting. Sheet piling is taken off by the
surface area to be braced or sheet-installed.
Wood sheet piling is purchased by board feet, steel pil-
ing by 100 pounds (cwt), and concrete piling by the piece.
Depending on the type used, the quantity of materials
required must also be determined.
Sheet piling may be placed in the excavation and braced
to hold it erect, or it may be driven into the soil. No one way
is less expensive. Often, after the work is done, the piles are
removed (pulled).Pulling may require the employment of a
pile extractor for difficult jobs, or hand tools for the simple
jobs. Figure 9.43 gives approximate requirements for labor
when placing sheet piling.

Estimating. The first step is to determine exactly what
type and shape pile is required; next, the number of piles
required; and third, decide the depth that the piles will have
to be driven. With this information, the estimator can deter-
mine material quantities and their cost.
If the contractor’s crew will drive the piles, the next
determination should be the type of equipment required,
how many hours the work will take, and cost per hour. Then
the crew size, along with the hours and cost per hour
required, is calculated. To arrive at this, an estimate of the
linear footage placed per hour (including all cutting off,
moving around, etc.) must be made so that the total number
of hours required for the completion of the pile driving is
determined. In dealing with sheet piling, if the sheets are to
be pulled at the end of construction, the estimator must also
include a figure for this. Costs must also comprise mobiliza-
tion of workers, equipment, and material for pile driving,
and demobilization when the work has been completed.

FIGURE 9.42.Driving Bearing Piles.

FIGURE 9.43.Sheet Piles, Approximate Hours Required.
Free download pdf