Project Resources and Quantities
In this project we have executed huge quantity of work in
record time and we have outlined the total quantities and
shown RCC, fabrication, and erection figures month-wise.
RCC – 87,756 CuM, fabrication – 10,833 MT, erection
- 19,567 MT, cable laying – 673 km, refractory – 6,476
MT, insulation – 27,640 sqm, and railway track laying –
1.258 km
10851548736
7257952210500
8220
69043450
2675 2216 2722 2605 2658 2475 3180020004000600080001000012000RCC in CuM