Project Resources and Quantities
In this project we have executed huge quantity of work in
record time and we have outlined the total quantities and
shown RCC, fabrication, and erection figures month-wise.
RCC – 87,756 CuM, fabrication – 10,833 MT, erection
- 19,567 MT, cable laying – 673 km, refractory – 6,476
MT, insulation – 27,640 sqm, and railway track laying –
1.258 km
108
5154
8736
7257
9522
10500
8220
6904
3450
2675 2216 2722 2605 2658 2475 3180
0
2000
4000
6000
8000
10000
12000
RCC in CuM