KILN ERECTION 75


Kiln shell under manufacturing at
FLSmidth

Kiln shell in transit passing
through barrier

Kiln shell received at RGP gate Kiln shell under assembly at RGP site

Receipt of 1st Over Dimension Consignment (ODC) of kiln
shells was an epic story. Preparations on a war-front basis
were started six days before receipt of material at the site. The
following arrangements were made for receipt of kiln shells:


•   Joint survey of entry path from Liploi Main Road
Junction to unloading location near kiln piers. The
survey team was led by our site head and the team
comprised of members from mechanical, civil, E&I,
and security
• Preparation of hard-soiling road (suitable to sustain
150 MT truckload) and widening of road turnings
• Removal of mechanical equipment and civil material
lying near the path