KILN ERECTION 79


Making way for eight trucks and unloading

Both vehicles were passed below the power supply line well
within the given time. Then both the vehicles were taken to
the unloading location and finally unloaded on the bed at
midnight giving a tremendous sense of satisfaction.
All balance vehicles for kiln shells and tyres were
escorted 11 km prior to project premises, with their entry
only in the night hours to avoid any local hindrance. With
commendable teamwork, all ODC were taken inside the
project premises, minimizing any traffic bottlenecks during
daytime.