Analogous Estimating


Analogousestimatingisatechniqueforestimatingthedurationorcostofanactivityoraproject
usinghistoricaldatafromasimilaractivityorproject.Analogousestimatingusesparametersfroma
previous,similarproject, suchasduration,budget,size, weight,andcomplexity,as thebasisfor
estimatingthesameparameterormeasureforafutureproject.Whenestimatingdurations,this
techniquereliesontheactualdurationofprevious,similarprojectsasthebasisforestimatingthe
durationof thecurrent project.Itis agross value-estimating approach,sometimes adjustedfor
known differences in project complexity. Analogous duration estimating is frequently used to
estimateprojectdurationwhenthereisalimitedamountofdetailedinformationabouttheproject.
Analogousestimatingisgenerallylesscostlyandlesstime-consumingthanothertechniques,butitis
alsolessaccurate.Analogousdurationestimatescanbeappliedtoatotalprojectortosegmentsofa
projectandmaybeusedinconjunctionwithotherestimatingmethods.Analogousestimatingismost
reliablewhenthepreviousactivitiesaresimilarinfactandnotjustinappearance,andtheproject
teammemberspreparingtheestimateshavetheneededexpertise.


92 .Answer:C.


PMBOK® Guide, pages 244 – 245 , Section 7. 2. 2. 5


Three-PointEstimating


...


Depending on the assumeddistribution ofvalues within the range ofthe threeestimates, the
expectedduration,tE,canbecalculatedusingaformula.Twocommonlyusedformulasaretriangular
andbetadistributions.Theformulasare:


o Triangulardistribution.tE=(tO+tM+tP)/ 3


o Betadistribution(fromthetraditionalPERTtechnique).tE=(tO+ 4 tM+tP)/ 6


Durationestimatesbasedonthreepointswithanassumeddistributionprovideanexpectedduration
andclarifytherangeofuncertaintyaroundtheexpectedduration.


93 .Answer:B.


PMBOK® Guide, pages 244 – 245 , Section 7. 2. 2. 5


Three-PointEstimating


...


The accuracy of single-point duration estimates may be improved by considering estimation
uncertaintyandrisk.Usingthree-pointestimateshelpsdefineanapproximaterangeforanactivity's
duration:


o Mostlikely(tM).Thisestimateisbasedonthedurationoftheactivity,giventheresourceslikelyto
beassigned,theirproductivity,realisticexpectationsofavailabilityfortheactivity,dependencieson
otherparticipants,andinterruptions.


o Optimistic(tO).Theactivitydurationbasedonanalysisofthebest-casescenariofortheactivity.


o Pessimistic (tP). The duration based on analysis of the worst-case scenario for the activity.
Dependingontheassumeddistributionofvalueswithintherangeofthethreeestimates,the
expectedduration,tE,canbecalculated.Onecommonlyusedformulaistriangulardistribution:tE