scheduleconstraint–canalsobedetermined.Forexample,thefreefloatforActivityB,inFigure 6 –
18 ,isfivedays.
- Answer: B.
PMBOK®Guide,page 222 ,Section 6. 6
Control Scheduleis the process of monitoringthe status ofthe project to update the project
scheduleandmanagingchangestotheschedulebaseline.Thekeybenefitofthisprocessisthatthe
schedulebaselineismaintainedthroughouttheproject.Thisprocessisperformedthroughoutthe
project.